Form 1

Parties to Dispute:

Dispute: Claim of Employes:

NATIONAL P,AILROAD ADJUSTMENT BOARD Award No. 8507
SECOND DIVISION Docket No. 8477
2-MP-EW-180

International Brotherhood of Electrical Workers

Missouri Pacific Railroad Company



That, accordingly, the Missouri Pacific Railroad Company be ordered to compensate Comanunications maintainer J . J . aoggard two and seventenths hours (2.7') at the overtime rate for I-lay 16, 1978.

Statement:

The above question was submitted to the Second Division of the National Railroad Adjustment Board by the a.'.:ove referred to organization in ex pane form, hearing thereon vas waived, and the Division is now in receipt of a request from the employes that the case be withdrawn.

A W A R D

Claim dismissed.

Attest: Executive Secretary
National Railroad Adjustment Board

NAT IONTAL RAIIdZOAD ADJUSTMENT BOARD

By Order of Second Division




..~'ated at Chicago, Illinois this 19th day of November, 1980.
D