Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 
8508
  
SECOND DIVISION Docket No. 
8478
  
2 -MP-EW-' 80
 
( International Brotherhood of Electrical Workers
Parties to Dispute:
 
( Missouri Pacific Railroad Company
Dispute: Claim of Employes:
1. That the Missouri Pacific Railroad Company violated Rules 
3, 4 -
Section 1 (a), 
5 (a), 6 
(a) and (b), 
7 
((a), (d) and (g) of the
Coirnnunications Agreement effective August 
1, 1977 
when they denied
Communications Maintainer C. Legamaro at St. Louis, Missouri the
overtime provisions of the Agreement:, i.e., four and seven-tenths
hours 
(4.7') 
at the overtime rate for work performed outside his
bulletined hours - 9:30 p.m. to 11:30 P.m., May 
28, 1978, 
and a
holiday 
7:30 
a.m. to 9:30 a.m., May 
29, 1978.
2. That, accordingly, the Missouri Pacific Railroad Company be ordered to
compensate Communications Maintainer C. Legamaro four and seven-tenths
hours 
(4.7') 
at the overtime rate for May 28, and 
29, 1978.
Statement:
The above question was submitted to the Second Division of the National
Railroad 
Ac.justment Board 
by the above referred to organization in ex parte
form, hearing thereon was waived, and the Division is noia in receipt of a
request from the employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTNIENT BOACtiI
 
By Order of Second Division
Attest: Executive Secretary
 
National Railroad Adjustment Board
dr
By _'...;,~x,-"..-_~.,.~_ ...  ~·a,.E:._.a
,o-°` 
,:osemarie Brasch - Administrative Assistant
Ile
../Dated at Chicago, Illinois, this 19th day of November, 
1980.