Dispute: Claim of Employes:
NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 8540
SECOND DIVISION Docket No.
8281-T
2-MP-SM-'80
The Second Division consisted of the regular members and in
addition Referee David H. Brown when award was rendered.
( Sheet Metal Workers' International Association
Parties to Dispute:
Missouri Pacific Railroad Company
1. That the Missouri Pacific Railroad Company violated the controlling
Agreement, particularly Rules
26(a), 97
and Article V, Sections A,
C, D, and G, when on December
2, 1977,
other than Sheet Metal Workers
were assigned the disconnecting and connecting of pipes to diaphrams
on air compressor at Center Air Compressor Room, Kansas City Diesel
Shops, Kansas City, Missouri.
2. That accordingly the Missouri Pacific Railroad Company be ordered to
compensate Sheet Metal Worker C. E. Straw eight
(8)
hours at double
time rate of pay for such violation,
Findings:
The Second Division of the Adjustment Board, upon the whole record and all:
the evidence, finds that:
The carrier or carriers and the
are respectively carrier and employe
Act as approved June
21, 193..
employe or employes involved in this dispute
within the meaning of the Railway Labor
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
This case is indistinguishable from that
in
Award No.
8539.
Carrier
properly handled the work assignment under Rule 52.
A W A R D
Claim denied.
Attest: Executive Secretary
National Railroad Adjustment Board
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
3By osemarie Brasch - Administrative Assistant