The Second Division consisted of the regular membars and in
 
addition Referee Herbert L. Marx, Jr. when award was rendered.
  
( International Brotherhood of Electrical Workers
Parties: to Dispute
 
( Missouri Pacific Railroad Company
Dispute: Claim of Employes:
1. That the Missouri Pacific Railroad Company violated Rules 
3, 
4-Section.
 
1 (a), 5 
(a), 6 
(a), and 
7 
(a), (d) and (g) of the Com.-unications Agreement
 
effective August 
1, 19(7 
when they denied Communications Maintainer. L. E.
 
Sailors at G~iha, Nebraska the overtimz provisions of the Agreement, i..e.,
 
two and seven-tenths hours (2.7') at the overtime rate for work performed
 
outside his bulletined hours on April 14, 
1978.
2. That, accordingly, the Missouri Pacific Railroad Company be ordered t0
compensate Commranicat%ons Maintainer L. E. Sailors two and seven-tentfl!s
hours (2. 7' ) at the overtiuas rate for April 14, 
1978.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex parte form,
hearing thereon was waived, and the Division is now in receipt of a request from
the employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL 
RAILROAD ADJUSTMENT BOARD
 
By Order of Second Division
Attest: Executive Secretary
 
National Railroad Adjustment Board
By ,---~'z.C-'~-C~-
-----Rommrie Brasch - Administrative Assistant
Dated at Chicago, Illinois, this 2 1st day of January, 