Form 1 NATIONAL RAILROAD ADJLSTIENT BOARD Award No.
8588
SECOND DIVISION Docket No.
8625
2-MP-EW-' 81
The Second Division consisted of the regular members and in
addition Referee David P. Twomey when award was rendered.
( International Brotherhood of Electrical Workers
Parties to Dispute:
( Missouri Pacific Railroad Company
Dispute: Claim of Employes:
1. That the Missouri Pacific Railroad Company violated Rules 3, 4 - Section
1 (a), 5 (a),
6
(a) and (b),
7
(a), (d) and (g) of the Communications
Agreement effective August 1,
1977
when they denied Communications
Maintainer R. D. Babylon at Kansas City, Missouri the overtime provisions
of the Agreement, i.e., for work performed on Monday, September 4,
1978,
a holiday.
2. That, accordingly, the Missouri Pacific Railroad Company be ordered to
compensate Communications Maintainer R. D. Babylon two and seven-tenths
hours
(2.7')
at the overtime rate for Monday, September
4, 1978.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex parte fort,
hearing thereon was waived, and the Division is nova in receipt of a request from
the employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest: Executive Secretary
National Railroad Adjustment Board
By
l: semarie Brasch - Administrative Assistant
Date at Chicago, Illinois, this 21st day of January,
1981.