NATIONAL RAILROAD ADJUSTME'a'T BOARD Award No.
8597
SECOND DIVISION Docket No.
8791
2-MP-E4-181
The Second Division consisted of the regular members and in
addition Referee Gilbert H. Vernon when award was rendered.
( International Brotherhood of Electrical Workers
Parties to Dispute:
~ Missouri Pacific Railroad Company
Dispute: Claim of Employes:
1. That the Missouri Pacific Railroad Company violated Rules
3, 4
- Section
1 (a), 5 (a),
6
(a),
7
(a), (d) and (g) of the Communications Agreement
effective August 1,
1977
when they denied Communications Maintainer H,. G.
Heise at Dupo, Illinois the overtime provisions of the Agreement,
Leo,
two (2) hours at class
3
overtime for work performed outside his bulletined
hours on February
14, 1979.
2,
That, accordingly, the Missouri Pacific Railroad Company be ordered to
compensate Communications Maintainer H. G. Heise two (2) hours at class
overtime for February
14, 1979.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex parte form,
hearing thereon was waived, and the Division is now in receipt of a request from
the employes that the case be withdrawn.
A W A R D
Claim dismissed.
Attest: Executive Secretary
National Railroad Adjustment Board
BY
Rosemarie Brasch - Administrative Assistant
Dated at Chicago, Illinois, this 21st day of January,
1981.
NATIONAL RAILROAD ADJUSTriENT BOARD
By Order of Second Division