Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 869~7
SECOND DIVISION Docket No. 871$
2-B&o-CM-' 81
The Second Division consisted of the regular members and in
addition Referee Gilbert H. Vernon when award was rendered.
Brotherhood Railway Carmen of the United States
Parties to Dispute:
and Canada
( Baltimore and Ohio Railroad Company
Dispute: Claim of Employes:
No. 1. That under the controlling Agreement the Carrier-failed to call the
Cumberland assigned wrecking crew for work in connection with a
derailment at Orleans Road a location approximately twenty-three (23)
miles East of Cumberland, Maryland on the date of December
15, 1978.
The Carrier enlisted the service of an outside contractor, Hulcher
Emergency Service, and allowed them to perform, not only carmens wrecking
work, but also carmen's work contractually recognized as such,
exclusively.
No. 2. That the Carrier failed to comply with the rules of the controlling
Agreement, specifically, Rules 29, 138, and 142 of the Shop Crafts'
Agreement, as well as Article VII of the December 4, 1975 Agreement,
Wrecking Service Rule, effective March 27, 1976.
No. 3. That accordingly the Carrier be ordered to compensate the following
identified employes for their losses arising out of this incident;
L. B. Mathias, A. T. Rice Jr., P. H. Sibley, W. C. Shaffer, G. R.
Shafferman, A. F. Hinkle, J. E. Bierman, and J. E. Price, each, for
twelve hours pay at the time and one-half rate and eight hours pay at
the doubletime rate; L. D. Saville and R. H. Schxiver, each, for
eight hours pay at the time and one-half rate and eight hours pay at the
doubletime rate; W. D. Rawnsley, H. E. Fraley, and E. F. Ellis, each,
for eight hours pay at the time and one-half rate and four hours pay at
the doubletime rate; S. E. Teets, for twenty hours pay at the time and
one-half rate.
Findings:
The Second Division of the Adjustment Board, upon the whole record and all
the evidence, finds that:
The carrier or carriers and the employe or employes involved in this dispute
are respectively carrier and employe within the meaning of the Railway Labor Act
as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
On December 15, 1978, at approximately 2:10 p.m., a derailment occurred
along Carrier's tracks at "Orleans Road", a point approximately 23 miles from
Form 1 Award No.
8697
Page 2 Docket No.
8748
2-B&o-CM-'
81
Cumberland, Maryland and
77
miles from Brunswick, Maryland. The derailment
involved thirteen cars. The Carrier called Hulcher Emergency Service and the
Carrier's own wrecking crew from Brunswick to the scene. The issue to be dealt
with in this case is whether the Claimants had a contractual right to be called
to the derailment in lieu of the Hulcher Emergency Service used by the Carrier.
The Organization primarily supports its claim by its reading of Article VII
which states:
"...
1. When pursuant to rules or practices, a carrier
utilizes the equipment of a contractor (with or without
forces) for the performance of wrecking service, a
sufficient number of the carrier's assigned wrecking
crew, if reasonably accessible to the wreck, will be
called (with or without the carrier's wrecking equipment
and its operators) to work with the contractor. The
contractor's ground forces will not be used, however,
unless all available and reasonably accessible members
of the assigned wrecking crew are called. The number of
employees assigned to the carrier's wrecking crew for
purposes of this rule will be the number assigned as of
the date of this Agreement
..."
The Organization argues that the use of the contractor violated Article VII
because they were not called to work with the Brunswick crew. It is argued that
Article VII allows the use of a contractor only in conjunction with Carrier's
forces. In this case,it is suggested that at no time did Hulcher work with the
Carrier's forces. This was a result of the Hulcher crew working at one end of the
derailment and the Brunswick crew at the other. The Brunswick crew worked
separately and therefore not with the contractor, they assert.
The Carrier makes a threshold argument that the claim should be barred as a
result of a procedural defect. The Carrier contends that the Organization
significantly altered the basis for the claim during its appeal on the property.
The Carrier further argues without prejudice to their position on the
procedural defect, that Article VII only requires the Carrier to call the assigned
wrecking crew in a singular sense. only one crew has to be called, asserts the
Carrier, in order to comply with Article VII. The Brunswick crew was the assigned
crew and therefore no violation of Article VII can be established. In support of
this contention, they cite Second Division Award
8106
which in the Board's opinion
is principally identical to the facts in the instant case. The award is quoted
in pertinent part:
"Article VII sets down several conditions for the use of
a Carrier's wreck crew when the carrier uses a contractor's
equipment: 1) 'a sufficient number of the Carrier's assigned
wrecking crew, if reasonably accessible to the wreck will
be called
...
to work with the contractor'; 2) The Carrier's
assigned wrecking crew will be called. 'with or without the
Carrier's wrecking equipment and its operators'; and
3)
Form 1 Award No.
8697
Page 3 Docket No.
8748
2-B&o-CM-'
81
'The contractor's ground forces will not be used, however,
unless all available and reasonably accessible members of
the assigned wrecking crew are called.'
Applying these three conditions and Rule
96
to the instant
case we find the Carrier called out the Hagerstown Wreck
Train and regularly assigned crew. This met the requirement
of Rule
96.
It also met conditions 1 and 2 of Article VII;
that is, Carrier called out the Hagerstown 'assigned wrecking
crew' with its own 'wrecking equipment and its operators.'
The critical issue remaining, however, is whether or not
calling the members of the Port Covington crew, Carrier
failed to comply with the third condition set forth in
Article VII; namely, 'the Contractor's ground forces will
not be used, however, unless all available and reasonably
accessible members of the assigned wrecking crew are called.'
We hold that Carrier did comply with the terms of Rule
96
and Article VII. The Hagerstown 'assigned wrecking crew',
in its entirety, was called to work with the Contractor's
equipment and crew. In essence, therefore, we interpret
the references in Article VII to 'the Carrier's assigned
wrecking crew', 'the assigned wrecking crew', and 'the
Carrier's wrecking crew' as a crew in the singular and not
in the plural; i.e. a crew at a specific location on
Carrier's property and not to all wrecking crews at all
locations on Carrier's property where wrecking crews have
been established and/or designated. This construction is
borne out by the language of the NOTE to Article VII which
also refers to wrecking crew in the singular."
The Board must first address itself to the Carrier's procedural argument.
It is the Board's opinion that no fatal defect exists.
In considering the contentions of the parties as they related to the merits,
it must be said that it seems initially that Award
8106
is dispositive of the
issue. Award
8106
is accurate in its interpretation of Article VII that only one
wreck crew be assigned when a Carrier utilizes outside forces in a derailment and
when two crews are reasonably accessible. Further, it is seen as applicable because
the organization's attempt to distinguish the instant case is without reasonable
foundation. The Organization sought to establish a violation on the basis that
the Hulcher crew did not work "with" Carrier forces. This attempt is strained
in light of the facts. The Brunswick crew and the Hulcher crew, although they
worked from different ends of the derailment worked the same derailment and at
the same time.
Although Award
8106
seems dispositive of the instant issue, the Organization
cited Second Division Award
8284
which raises the possibility that the Carrier can
violate the agreement in their choice of which of two Carrier crews to assign
when they both are reasonably accessible. The Board in Award
8284
endorsed Award
Form 1 Award No.
8697
Page 4 Docket No.
8748
2
-B&o-CM-'
81 ''err
8106
in the respect to its holding that the Carrier need only assign one crew
but added some other considerations. The Board stated:
"Given our previous findings in Award
8106
that a carrier is
not obligated under Article VII of the December 4,
1975
Agreement to call more than one (1) assigned wrecking crew,
we now additionally add that where more than one assigned
wreckin crew is determined to be reasonably accessible to the
wreck, all other things being equal ceteris paribus),
Carrier is obligated under Article VII to call the crew
whose consist contains
a
number of wrecking crew members
sufficient to perform the wrecking service work. Emphasis added)
In so finding, we are of the belief that the determination
as to which of the reasonably accessible assigned wrecking
crews is of sufficient size (in those situations where more
than one wrecking crew is reasonably accessible to the wreck,
with all other things being equal), should be based, among
other consideration, on the size of the independent contractor's
crew arranged for by carrier relative to the comparative
differences in crew size among the eligible wrecking crews.
These determinations should be made on a case by case
basis."
In reviewing the instant case, in light of Award
8284,
however, we find no
evidence or existence of any of the considerations referred to therein that would
distinguish the instant case from Award
8106.
For instance, the primary consideration in Award
8284
seemed to be the fact that Hulcher crew outnumbered the Carrier's
crew. It was stated:
"In the case at bar, the Carrier had a choice of at least
two
(2)
assigned wrecking crews that we know of which were
considered to qualify as being reasonable accessible to the
wreck. Carrier exercised its prerogative and chose the
smaller crew and the one based the furthest distance away
from the derailment site. We might not have cast any
objeations to Carrier's choice of wrecking crews here no
matter how dubious such choice may appear to be to us on
the surface, had it not been for the fact that the crew
arranged for by Carrier and provided by Hulcher, the
independent contractor, outnumbered Carrier's crew by
slightly more than two
2
to one 1 ." Emphasis added)
There is no suggestion by the Organization nor is there any evidence in the record
that the Hulcher crew outnumbered the assigned crew in the instant case.
In conclusion, because there is nothing in the instant record that would
distinguish the instant case from Award
8106,
it therefore is held to be controlling.
Form 1 Award No.
8697
Page
5
Docket No.
8748
2-B&O-CM-'81
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest: Executive Secretary
National Railroad Adjustment Board
5By
emerie Brasch - Administrative Assistant
Dated t Chicago, Illinois, this 29th day of April,
1981.