Form 1 NATIONAL RAIZR.OAD ADJUSTMENT BOARD Award No. 8827
SECOND DIVISION Docket No. 8743
2-B&O-CM-'81
The Second Division consisted of the regular members and in
addition Referee Gilbert H. Vernon when award was rendered.
Brotherhood Railway Carmen of the United States
Parties to Dispute: arid Canada
( Baltimore and Ohio Railroad Company
Dispute: Claim of Employes:
No. 1. That under the terms of the Controlling Agreement the Carrier failed to
call the Cumberland "assigned wrecking crew" to a derailment of twentyfour (24) cars, on the date of October 26, 1978, to Mud Pike Crossing
on the S & C Branch Line, at which time the Carrier enlisted the servj:ces
of two (2) outside contractors, Svonavec Construction Company, and Perm
Erection Company, and utilized five
(5)
carmen, not members of an
assigned wrecking crew, out of Somerset, Pennsylvania.
No. 2. That the Carrier failed to comply with the rules of the controlling
Agreement, specifically, Rule 142,
138,
Article VII of the December 4_
1975 Agreement and Article V, SUBCONTRACTING, as amended in the Decemt>er
4,
1975 Agreement, Section 1 (a) of Article II.
No. 3. That accordingly the Carrier be ordered to compensate the following
claimants for their losses arising out of this incident: Z. B. Mathias,
A. T. Rice Jr, P. H. Sibley, W. C. Shaffer, G. R. Shafferman, L. D.
Saville, S. E. Teets, A. F. Hinkle, W. D. Rawnsley, J. E. Bierman,
J. E. Price, R. H. Schriver, each, for twelve hours pay at the time
and one-half rate and three and one half hours at the doubletime rate,;
H. E. Fraley for eight hours pay at the time and one-half rate and
eight hours pay at the doublAitime rate; E. F. Ellis for eleven and
one-half hours pay at the time and one-half rate and four hours pay
at the doubletime rate.
Findings:
The Second Division of the Adjustment Board, upon the whole record and all
the evidence, finds that:
The carrier or carriers and the employe or employes involved in this dispel=e
are respectively carrier and employe within the meaning of the Railway Labor Act,
as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The facts are not essentially disputed. On October 27, 1978, a derailment
involving 24 cars occurred at Mud Pike Road crossing, which is approximately 2
miles from Somerset, Pennsylvania. The Carrier called two outside contractors,
Form 1 Award No.
8827
Page 2 Docket No.
87+3
2 -B&o-crt-'
81
the wrecking crew from Connellsville and
5
carmen and a foreman from Somerset,
Pennsylvania. The claim in this case is for the Cumberland wrecking crew which
is about 40 miles from the scene of the derailment.
The most pertinent portion of the contract is Article VII of the December
4,
1975
Agreement which states:
"When pursuant to rules or practices, a Carrier utilizes try
equipment of a contractor (with or without forces) for the
performance of wrecking service, a sufficient number of
the Carrier's assigned wrecking crew, if reasonably
-
accessible to the wreck, will be called (with or without
the carrier's wrecking equipment and its operators) to
work with the contractor. The contractor's ground forces
will not be used, however, unless all available and reasonably
accessible members of the assigned wrecking crew are called.
The number of employes assigned to the carrier's wrecking crew
for the purposes of this rule will be the number assigned as
of the date of this Agreement.
NOTE: In determining whether the carrier's assigned
wrecking crew is reasonably accessible to the
wreck, it will be assigned that the ground men
of the wrecking crew are called at approximately
the same time as the contractor is instructed to
proceed to the work. Emphasis added) -
Article VII has been the subject of several strong disagreements between this
Organization and the Carrier. The parties, as previously noted in Award
8106,
have widely divergent views on its meaning. This case is no exception. However,
before we can approach the merits of this case there is at the threshold a procedural
argument that must first be addressed. At the Board, the Carrier member registered
an objection contending that the claim as presented to the Board in exparte
submission form changed from the claim as presented on the property. It was
argued the claim was argued on a basis at the Board which was entirely different
than the basis it was argued on the property. It was argued in this connection
that "it is also an established maxim that a claim cannot be one thing on the
property and another thing before the Board. Petitioner must permit Carrier on
the property the opportunity to answer all contentions relative to a dispute."
The Carrier's objections refer to the following argument by the Organization in
their exparte submission:
"It is an undisputed fact that the claimants in the instant
claim are, in fact, assigned wreck crew members, were available
and reasonably accessible and were entitled to be called in
compliance with the herein quoted Article VII. It is the
position of the Employes, that the arbitrary action on the
part of the Carrier whereas they enlisted the services of two
outside contractors to perform work accruing to the Carrier's
assigned wrecking crew, readily available and reasonably
accessible, undisputedly so, is a direct and flagrant violation
Form 1 Award No.
8827
Page
3
Docket No.
87+3
2-BSoo-CM-' 81
of Article VII--Wrecking Services--December
4, 1975
Agreement.
The Carrier ignored the contractual rights of its own Employee
and contracted the work to two (2) outside contractors, Svonavec
Company and Penn Erection Company, when in fact, Article VII
specifically refers to one and only one contractor. The word
contractor as used in Article VII refers to one contractor in
the singu ar. Had the authors of this rule intended. for the
Carrier to enlist the services of more than one contractor,
it is apparent to this Organization, they would have uLad he
word contractors, in the plural. However, there are no
provisions in Article VII whereas the Carrier is permitted to
call more than one contractor as in the instant case, when in
fact the Carrier s own Cumberland assigned wrecking crew and
_ equipment stood ready and available, and more than reasonably
accessible to the wreck." (Underscoring added by Organization)
This argument was elaborated by the labor member in the following way:
"In this instant case the Carrier states its position regarding the
word 'the' which is suppose to mean 'one' ie; si lar, meaning
the Carrier would meet the requirements of the Agreement by
calling 'the " one' 'single' assigned wrecking crew to work with
the contractor
s
groLmd forces.
Using this same Carrier's reasoning regarding the words 'the'
'sin le' we now refer to Article VII in pertinent part:
'.
. . A Carrier utilizes the equipment of a contractor
. . . to work with the contractor. The contractor's
ground forces will not be used, unless all available
and reasonably accessible members of the assigned
wrecking crew are called.'
It has always been the Carrier's position that 'the Crew
means one (1) crew the agreement does not specify 'Crews'
we cannot change from the 'singular crew' to plural crews
ie; more than one.
Applying this same philosophy to 'the contractor' as referred
to in Article VII, if we cannot change 'the crew' to mean more
than one crew how then can the Carrier change the meaning of
the words 'the contractor' to mean more than one. In order to
be consistent with its own argument the Carrier cannot deny
nor interpret the meaning of the words 'the contractor' to mean
more than one. Had the authors of the Agreement intended to give
the Carrier the right to call more than one contractor they would
have so stated by stating:
'to work with the contractors they instead say . . . . .
to work with the contractor.'
Form 1 Award No. 8827
Page
4
Docket No. 87+3
2-B&o-CM-'81
In this instant case the Carrier called more than one contractor
it called two contractors in doing so this Carrier was obligated
to call two assigned wrecking crews. The claimants are regular
assigned members of the Cumberland Wrecking Crew and were all
available and reasonably accessible and should have been called."
It is the above mentioned argument and the implication that for each contractor
the Carrier should assign one wrecking crew, that the Carrier Member says was not
made on the property. This, .it is argued, changes the nature of th.: claim to a
degree that the claim must be dismissed. The Labor Member vigorously argued in
rebuttal to the Carrier's procedural argument that the "one crew for one contract"
or "singular" vs. "plural" argument was in fact made on the property. The
Referee's attention was directed to employee exhibit "E", which is a letter from
the General Chairman to the Carrier's designated officer. It was asserted that
a reading of exhibit "E" conclusively shows the argument was made on the property.
It was further asserted that this is so because the argument was anticipated in
Carrier's exparte submission and that the Carrier should have made their objection
earlier.
In reviewing the competing arguments and after carefully reviewing the record
including exhibit "E", it cannot be reasonably concluded that the claim now being
argued before the Board was argued on the same basis as it was on the property.
The "one crew for one contractor" or "singular vs. plural contractor" theory was
not advanced by the General Chairman on the property. A reading of exhibit "E"
finds that the General Chairman on the property only mentioned the fact that two
contractors were used but did not make any direct reference to the "singular vs.
14rl1
plural" or wore crew for one contractor" argument. The fact and the theory are
two different things and because the fact was mentioned it doesn't follow the
theory based on that fact was automatically advanced. If the General Chairman
meant for this letter to make that "singular vs. plural" argument they have
a positive obligation to state the basis of the claim clearly enough that it
can be said that the Carrier had an opportunity to respond. Throughout the
handling of the claim on the property, the Organization primarily relied on two
theories as to why the wrecking crew at Cumberland should have been called. These
arguments were entirely different from the "singular vs. plural" theory or the
"one crew for one contractor" theory. First, they argued that the Cumberland
wrecking crew should have been called instead of the carmen from Somerset and
second that the Carrier didn't call s sufficient number of the assigned wrecking
crew. These arguments were still made in the exparte submission but the "one
crew for one contractor" theory was added and seems to be given a primary role.
Having found that the basis or theory on which the claim was advanced on the
property was different than the basis on which it w1s advanced at the Board, it
must be considered whether this precludes us from considering the case based on
its merits. It is our conclusion that we are compelled to dismiss the claim. This
is consistent with the long standing precedent of this Board that the Railway
Labor Act requires that the basis of a claim as handled on the property cannot
be significantly altered on appeal to the Board. This is an appellate tribunal
and our function is to consider disputes on the same basis as the parties
themselves consider them. We understand the potential frustration the Claimants
may find in not having their "day in court" on the merits. However, it would be
Form 1 Award No.
8827
Page
5
Docket No.
87+3
2-B&O-CM-'81
unworkable if our decisions were based on arguments one side or the other did
not have an opportunity to respond to. Additionally, if we did, the Board's
thinking would be short sighted and potentially inaccurate as a result of not
having issues fully enjoined by the parties. Such a rule cuts both ways and s
decision such as this is in the best interest of both parties as it would be
erroneous and unfair if we were to hold that one party or the other's position
could be prejudiced by a surprise argument. In this regard we should note this
dismissal on a procedural basis in no way reflects on the merits of any arguments
properly or improperly made within this record.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest: Executive Secretary
National Railroad Adjustment Board
By
emarie Brasch - Administrative Assistant
Dated at Chicago, Illinois, this 2nd day of December,
1981.