Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 9613
SECOND DIVISION Docket No. 9612-T
2-NRPC-EW-'83
The Second Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
( International Brotherhood of Electrical Workers
Parties to Dispute:
( National Railroad Passenger Corporation
Dispute: Claim of Employes:
1. That the National Railroad Passenger Corporation violated the current
Agreement when it assigned Carman T. Bologna to operate transfer table
between track 4 and release track at the Albany/Rensselaer Facility on
May 1, 1980, in connection with removing and replacing, wheels on AM
Fleet 21129.
2. That accordingly, the National Railroad Passenger Corporation should be
ordered to compensate Electrician J. Brideau who was available but not
called, with four (4) hours pay at the applicable electricians' rate.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex parte form,
hearing thereon was waived, and the Division is now in receipt of a request from
the employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
Nancy J./tr - Executive Secretary
Dated at Chicago, Illinois, this 14th day of September, 1983.