Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 9624
SECOND DIVISION Docket No. 9696
2-CR-EW-'83
The Second Division consisted of the regular members and in
addition Referee Robert M. O'Brien when award was rendered.
( International Brotherhood of Electrical Workers
Parties to Dispute:
( Consolidated Rail Corporation
Dispute: Claim of Employes:
1. That the Consolidated Rail Corporation violated the current agreement,
especially Rule 2-A-4(b) when it failed to allow Electrician M. Hooley,
Avon Indiana Diesel Terminal, an additional two (2) hours straight time
pay at the applicable electrician's rate due him under Rule 2-A-4(b)
when carrier assigned him to perform work not comprehended in his regular
assignment on July 16, 1979, particularly to locating troubles on
locomotive 8052 that activated the ground relay.
2. That accordingly the carrier should be ordered to pay Electrician
M. Hooley an additional two (2) hours' pay at the applicable electrician's
straight time rate due him under Rule 2-A-4(b) in order to make him whole.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex parte form,
hearing thereon was waived, and the Division is now in receipt of a request from
the employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
Nancy ver - Executive Secretary
Dated at Chicago, Illinois, this 14th day of September, 1983.