Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 9645
SECOND DIVISION Docket No. 9880-T
2-NRPC-EW-'83
( International Brotherhood of Electrical Workers
Parties to Dispute:
( National Railroad Passenger Corporation
Dispute: Claim of Employes:
1. That under the current agreement the National Railroad Passenger
Corporation (Amtrak) improperly assigned a Laborer to work of changing
out diesel locomotive batteries at Albany/Rensselaer, New York Maintenance
Facility on December 18, 1979.
2. That accordingly, the National Railroad Passenger Corporation (Amtrak)
be ordered to compensate Electrician H. Palmer an additional four (4)
hours' pay.
Statement:
The above question was submitted to the Second Division
of
the National
Railroad Adjustment Board by the above referred to organization in ex parte form,
hearing thereon was waived, and the Division is now in receipt of a.request from
the employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
Z
ZIP
-.- /.,40
Nancy J. er - Executive Secretary
Dated at Chicago, Illinois-, this 14th day of September, 1983.