Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 9669
SECOND DIVISION Docket No. 9743
2-SCL-EW-'83
( International Brotherhood of Electrical Workers
Parties to Dispute:
( Seaboard Coast Line Railroad Company
Dispute: Claim of Employes:
1. That the Seaboard Coast Line Railroad Company violated the controlling
agreement, in particular Rule 4(c), (e) and 7(d) when Communication
Maintainer J. M. Blankenship was required to perform service after
his normal work day July 18, 1979 relative to attending Operating
Rule Meeting at Manchester, Georgia.
2. That accordingly, the Seaboard Coast Line Railroad Company compensate
Communication Maintainer J. M. Blankenship in the amount of two (2)
hours and forty (40) minutes at the overtime rate for service required
after his normal work day on July 18, 1979.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex parte
form, hearing thereon was waived, and the Division is now in receipt of a
request from the employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
~Z ~" "."g
Nancy J e r - Executive Secretary
Dated at Chicago, Illinois, this 21st day of September, 1983.