Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 9722
SECOND DIVISION Docket No. 9239-T
The Second Division consisted of the regular members and in
addition Referee Martin F. Scheinman when award was rendered.
( International Brotherhood of Electrical Workers
Parties to Dispute:
( Chicago, Milwaukee, St. Paul and Pacific Railroad Company
Dispute: Claim of Employes:
1. That the Chicago, Milwaukee, St. Paul and Pacific Railroad Company
violated the current agreement when it improperly assigned Blacksmith
Alex Ransaw and Carmen Archie Williams, Eugene Braun, and Ed Borkowski
to operate electric cranes in the Freight Car Shop at Milwaukee
Shops during the period from May 14, 1979 thru June 19, 1979. The
work herein claimed should have been properly assigned to Electrician
Helper Kenneth Morrow.
2. That the Chicago, Milwaukee, St. Paul and Pacific Railroad Company
be ordered to compensate the Claimant at the Electric Crane Operator's
rate at eight hours per day for the twenty three days on which the
Carrier violated the Agreement. The herein mentioned violation
occurred on the following dates:
Blacksmith Alex Ransaw: May 14, 15, 16, 17, and 18, 1979.
Cayman Archie Williams: May 21 and 22, 1979.
Cayman Eugene Braun: May 29, 30, and 31, 1979
& June 1, 4, 5, 6, 7, 8, 11, 12,
13, 14, and 15, 1979.
Cayman Ed Borkowski: June18 and 19, 1979.
Findings:
The Second Division of the Adjustment board, upon the whole record and
all the evidence finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the
meaning of
the Railway
Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
At the time this claim arose, Claimant, K. Morrow, held seniority as an
Electrician Helper - Crane Operator at Carrier's facilities in Milwaukee,
Wisconsin. On twenty-three days during the period May and June of 1979, Carrier
assigned one Blacksmith and three Carmen, who are not represented by the Organization,
to operate the overhead crane on the north end of Tracks One and Two in the
Freight Car Shop.
Form 1 Award No. 9722
Page 2 Docket No. 9239-T
2-CMSP&P-EW-'83
As a result of Carrier's actions, the Organization filed this claim. In
it the organization alleges that Carrier violated Rule 72 of the Agreement as
well as a Memorandum of Agreement dated January 1, 1961 when it failed to
assign the Claimant to operate the overhead crane on the days in question.
Rule 72 and the Memorandum read, in relevant part:
Rule 72 - Classification of Lineman
"Men employed as generator attendants, motor attendants (not
including water service motors) and substation attendants, who
start, stop, oil, and keep their equipment clean and change and
adjust brushes for the proper running of their equipment: power
switchboard operators, cool-pier car dampers and cool-pier conveyor
car operators in connection with loading and unloading vessels.
"This is to include operators of electric traveling cranes,
capacity 40 tons and over."
Memorandum of Agreement - January 1, 1961
"1. The names of employes carried on the Milwaukee Shops
Electric Crane Operators Seniority Roster as of December 31, 1960,
~r
will be added to the bottom of the Milwaukee Shops Electrician
Helpers Seniority Roster in the same order in which their names
appear on the Electric Crane Operators Seniority Roster and will
be given an arbitrary seniority date of January 1, 1961 on the
Electricians Helpers Seniority Roster."
"4. Failure of the senior qualified employe on furlough in
both classifications to respond for an unfilled new position or
vacancy in either classification will cause forfeiture of
seniority rights in both classifications."
The Organization contends that Rule 72 and the above Memorandum mandate
that all Crane Operator assignments be performed by Electricians. The Organization
notes, that at the time the work in question was assigned to a Blacksmith and
Carmen, Claimant had been furloughed as a Crane Operator. Furthermore, the
Memorandum of Agreement clearly requires that all Crane Operators will be
added to the Electrician Helpers Seniority Roster. In the Organization's
view, Claimant was, thus, entitled to any Crane Operator assignment which
arose during the time of his furlough.
In addition, the Organization argues that members of its craft have traditionally
operated cranes for many years. In fact, the Organization points out that in
1980 Carrier improperly attempted to assign a Carman to the duties of a Crane
Operator. When Carrier was advised of its error, it rectified the situation
by assigning an Electrician to the position of Freight Shop Crane Opeator.
Thus, the Organization concludes that Carrier has acknowledged that the operation
of cranes belongs to its craft. Accordingly, the Organization asks that the
claim be sustained and that the Claimant be appropriately compensated.
Form 1 Award No. 9722
Page 3 Docket No. 9239-T
2-CMSP&P-EW-'83
Carrier, on the other hand, asserts that neither Rule 72 nor the Memorandum
of Agreement apply to the facts of this case. Carrier argues that Rule 72
relates only to the operation of electric traveling cranes whose capacity is
forty tons or more. Here, Carrier points out, the Blacksmith and Carmen were
assigned to cranes whose capacity was less than forty tons. Thus, Carrier
contends that there is no Rule in the Agreement which specifically requires
that Electricians perform the work in question.
In addition, Carrier maintains that it has often assigned Carmen or Blacksmiths
to operate cranes when Electricians Helpers - Crane Operators were not available.
While the Claimant had been furloughed as a Crane Operator he had been recalled
as an Electrician Helper. Thus, in Carrier's view, Claimant was not available
to perform the duties of a Crane Operator during May and June 1979. Therefore,
Carrier concludes that the practice on the property supports its position.
Accordingly, it asks that the claim be denied.
This dispute centers on the applicability of Rule 72 to this case. If
Rule 72 applies, then the Organization need not prove the existence of an
exclusive past practice with respect to the work in question. However, it is
clear that Rule 72 is inapplicable to the facts of this claim. Rule 72 by its
very terms includes "operators of travelling cranes, capacity 40 tons and
over". The record evidence indicates that the cranes) in question had a
capacity of under forty tons. Whether they were in all other respects identical
to the larger capacity cranes is irrelevant. The language of the Rule is
clear and unambiguous. It applies only to the larger capacity cranes and not
to the ones which are the subject of this dispute.
In addition, the Memorandum of Agreement makes no reference to the duties
of a Crane Operator covered by its terms. It merely lists the procedures by
which those employees carried on the Crane Operators Seniority Roster will be
incorporated into the Electrician Helpers Seniority Roster. As such, it does
not support the Organization's position here.
Accordingly, in order to prevail, the Organization must prove that the
operation of cranes belongs exclusively, on a system-wide basis, to members of
its craft. It has not met this burden of proof here. The record reveals that
Carrier has assigned Carmen to perform the work of Crane Operators when Electrician
Helpers/Crane Operators were not available. Here, Claimant was regularly
assigned as an Electrician Helper during May and June of 1979. Thus, he was
not available to perform Crane Operator work during that same period of time.
As such, the Organization has not proven that members of its craft have exclusives
performed the disputed work.
Finally, we note that the Organization's reliance on various cited Awards
is misplaced. Simply stated, they apply to situations where either by Agreement:
or practice the employees had exclusively performed the work at issue at the
location in question. As noted above, the record reveals no such practice nor
Agreement support. Accordingly, the claim is denied.
Form 1 Award No. 9722
Page 4 Docket No. 9239-T
2-CMSP&P-EW-'83
A W A
R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By
Order of Second
Division
ATTEST:
i~t^~
e , __ e:::-
~0~gP4
Nancy ver - Executive Secretary
Dated at Chicago, Illinois, this 16th dad of November 1983.