Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 9753
SECOND DIVISION Docket No. 8644
2-SIRTOA-MA-'8.4
(Staten Island Rapid Transit Operating Authority
Parties to Dispute:
(International Association of Machinists
( and Aerospace Workers
Dispute: Claim of Employes:
1. The Staten Island Rapid Transit Operating Authority arbitrarily
violated the schedule agreement beginning August 25, 1978 and
continuing thru October 17, 1978 by withholding monies earned and
due certain employes as a means of discipline.
2. Accordingly, F. Bolognia, J. Marsetti, L. Russo, W. Ochmann, J.
Rutigliano, A. Bishop, H. Wilmers, F. Blackden, and P. Raggi should
be compensated an amount equal to the amount which was withheld as
a result of the violation plus interest at the rate of 6 per cent.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex parte
form, hearing thereon was waived, and the Division is now in receipt of a
request from the employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
,iC~
Nancy J r-Executive Secretary
Dated at Chicago, Illinois, this 11th day of January, 1984