Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 9795
SECOND DIVISION Docket No. 9968-T
2-HB&T-EW-'84


Parties to Dispute:


Dispute: Claim of Employer:

1. That the Houston Belt and Terminal Railway Company violated Rules 22,
23 (a), 99, and 100 of the September 1, 1949 controlling agreement when
they assigned Machinist Hicks between 7:00 a.m. to 11:00 a.m. on
Wednesday, November 11, 1981, to change reverser and power contactor on
Belt Unit 52 thereby depriving Electrician O. Wooldridge of his contractual
rights to said work under the provisions of the Agreement at Houston,
Texas.
2. That, accordingly, Carrier be ordered to compensate Electrician O.
Wooldridge two hours and forty minutes (2'40") at the overtime rate for
. Wednesday, November 11, 1981.

Statement:

The above question was submitted to the Second Division of the National Railroad Adjustment Board by the above referred to organization in ex parte form, hearing thereon was waived, and the Division is now in receipt of a request from the Employer that the case be withdrawn.








Attest: ~r

        Nancy .ever - Executive Secretary


Dated at Chicago, Illinois this 29th day of February, 1984