Form Z NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 9800
SECOND DIVISION Docket No. 9983-T
2-HB&T-EW-'84
( International Brotherhood of Electrical Workers
Parties to Dispute:
( Houston Belt and Terminal Railway Company
Dispute: Claim of Employes:
1. That the Houston Belt and Terminal Railway Company violated Rules 22,
23(a), 100, and 102 of the September 1, 1949 controlling agreement when
they assigned Laborer Pryor between 11:00 a.m. and 3:00 p.m. on
Saturday, November 14, 1981 to operate the overhead electrical traveling
crane to set a generator in Belt Unit 60 thereby depriving Electrician
J. Burney of his contractual rights to said work under the provisions
. of the Agreement at Houston, Texas.
2. That, accordingly, Carrier be ordered to compensate Electrician J.
Burney two hours and forty minutes (2'40") at the overtime rate for
Saturday, November 14, 1981.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex parte form,
hearing thereon was waived, and the Division is now in receipt of a request from
the Employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
Nancy 010-rver - Executive Secretary
Dated at Chicago, Illinois this 29th day of February, 1984