Form 1 NATIONAL RAILROAD ADJUSTMENT BOAAD Award No. 9801
SECOND DIVISION Docket No. 9984--T
2-HB&T-EW-'84
( International Brotherhood of Electrical Workers
Parties to Dispute:
( Houston Belt and Terminal Railway Company
Dispute: Claim of Employes:
1. That the Houston Belt and Terminal Railway Company violated Rules 22,
23 (a), 99, 100, and 102 of the September 1, 1949 controlling agreement
when they assigned Laborer Johnny Pryor and Laborer Barry Baker between
7:00 a.m. and 3:00 p.m. on Sunday November 1, 1981, to operate the
overhead electric traveling crane and install traction motor for Belt
Unit 34 thereby depriving Electrician J. Burney and Electrician T.
Cochran their contractual rights to said work under the provisions of
the Agreement at Houston, Texas.
2. That, accordingly, Carrier be ordered to compensate Electrician J.
Burney and Electrician T. Cochran eight (8) hours at the overtime rate
for Sunday, November 1, 1981.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex parte form,
hearing thereon was waived, and the Division is now in receipt of a request from
the Employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
Nancy J D~r - Executive Secretary
Dated at Chicago, Illinois this 29th day of February, 1984