Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD  Award No. 9803
 
SECOND DIVISION Docket No. 9986-T
   
2-HB&T-EW-'84
( International Brotherhood of Electrical Workers
Parties to Dispute:
( Houston Belt and Terminal Railway Company
Dispute: Claim of Employes:
1. That the Houston Belt and Terminal Railway Company violated Rules 22,
 
23 (a), 99, and 100 of the September 1, 1949 controlling agreement when
 
they assigned Machinist Childs between 7:00 a.m. and 12 noon on Tuesday,
 
November 3, 1981, to remove the main generator brushes on Belt Unit 60
 
thereby depriving 
Electrician T
. Cochran of his contractual rights
 
under the provisions of the Agreement at Houston, Texas.
2. That, accordingly, Carrier be ordered to compensate Electrician T.
 
Cochran two hours and forty minutes (2'40") at the overtime rate for
 
Tuesday, November 3, 1981.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex pane form,
hearing thereon was waived, and the Division is now in receipt of a request from
the Employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
 
By Order of Second Division
Attest:
Nancy . ~ver - Executive Secretary
Dated at Chicago, Illinois this 29th day of February, 1984