Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 9976
SECOND DIVISION Locket No. 9118
- , 2-C&NW-CM-' 84















































Form 1 Award No. 9976
page 2 Locket No. 9118
2-C&NW-CM-'84

Some additional .background is necessary. On this Carrier, Mechanics-inC.harge come under the Federated Crafts agreement, although not subject to certain rules of such agreement. They are monthly rated, and work 5 days one week, 6 days the next, for the monthly rate. Time worked outside assigned hours is paid for at overtime rate. For purposes of the Union Shop Agreement, incumbents of Mechanic-in-Charge positions are required to maintain union membership, and to the best of the Carrier's information maintain membership in the craft from which promoted. Almost without exception, Mechanics-in-Charge are selected from mechanics emplo,ed by the Carrier. Mechanics so appointed do not establish separate seniority as tlechanics-in-Charge, but retain and continue to accumulate seniority in their craft at ho,Te point.

In this case, the Carrier called the MIC Gary Dekan who was headquartered at Wausau, Wisconsin, to proceed to Eland, Wisconsin, to rerail three freight cars. He was joined by a Cayman from Green Bay, Wisconsin. The Organization. contends the CZainant should have been used in lieu of the l^.echanic-in-Charge.

Generally, the Organization takes the position that the Nlechanic-in-C1,arge is limited to the point employed. The Organization submits that Rules 10, 29, 53, and Memorandums of Agreement covering Rules 126 and 127 were violated. These rules read as follows:












































1
Form 1 Award No. 9976
Page 4 Locket No. 9118
2-C&NW-CM-'84 i(b) Where the use of the contractor's equipment as set forth in (a)
is contingent upon the contractor furnishing personnel other than
actual operators of such equipment, it is agreed that the carrier
will provide one carman for each man (other than operators) furnished
by the contractor (including in such count the 2-man minimum set
forth in (a)) with maximum of 6 men. Where contractor furnishes over
12 men other than operators than the maximum of C&PIWT carmer will be
increased to 8.
(c) The above requirements are contingent upon the carmen employes
being reasonably accessible to the wreck.
NOTE: In determining whether the carrier's assigned wrecking crew
is reasonably accessible to the wreck, it will be assumed
that the groundmen of the wrecking crew are called at
approximately the same time as the contractor is instructed
to proceed to the work.



































Form 1 Award No. 9976
Page S Docket No. 9118
2-C& NW-CM- ' 84














The Carrier takes the position that the Agreement of '-lay 23, 1939, which established Mechanics-in-Charge specifically stated that they will "be permitted to do any and all mechanics work." Further, it is =he .position of the Carrier that from 1939 to approximately the time the instant claim was initiated that %echanics-in-Ch-azge at outlying points have performed car and motive power work at points other than where headquartered, teat such performance has been known to the Organization, and that the propriety of such use had not previously been questioned. For instance, at the time negotiations were held leading up to the May 23, 1939 Agreement, the Carrier's records indicate there were a total of 32 working foreman (subsequently called Mechanics-in-Charge) employed by the Carrier in its Car Department. They attach as a Carrier Exhibit, a statement dated February 23, 1939 showing the locations at which assigned and the work performed by each. The Carrier calls the Board's attention to the fact that of the 32 N:echanics-in-Charge, 23 or 72% of such Mechanics-in-Charge performed road work, i.e. took care of bad order cars set out at points other than at the headquarters of the assignment at the time of the 1939 agreement. The Carrier's records clearly indicate that during the negotiations resulting in the May 23, 1939 Agreement, organization representatives never at any time contested the practice of Mechanics-in-Charge performing road work. They also emphasize that such Mechanics-in-Charge have in fact continued subsequent to May 23, 1939, to perform road work as indicated on their Exhibit A.

The Carrier also mentions that in an August 6, 1980 letter the Carrier made the following statements which they suggest remained unchallenged by the Organization:




Form 1 Award No. 9976
Page 6 Locket No. 9118
2 -C& NW-CM- ' 84

The Board has considered the arguments of the parties and have arrived at a number of threshold conclusions. The Carrier asserts that without rebuttal that Mechanics-in-Charge have done work away from their headquartered point. When this is considered in conjunction with the 1939 Agreement--which recognized the practice in effect at the time of Mechanics-in-Charge doing road work-there can be little doubt that MIC's can, generally speaking, do mechanics work on the line of road away from, their headquarters point.

However, beyond this threshold consideration it must be asked whether there is any specific exception elsewt-,ere in agreements between the parties which could be considered as reserving work in conjunction with derailments to Carmen to the exclusion of MIC's. In Award 9394 such a specific exception to the more general 1939 Agreement was found in the 3-1-76 Memorandum of Agreement relating to Rules 126 and 127. This exception related to derailments where contractors were utilized.

A further review of the Agreement including Rules 126, 127 and the P3emorandum related thereto fails to reveal any specific exception which would reserve work on the line of road in connection with derailments to Carmen under the circumstances.

The second paragraph of Rule 127 clearly would allow the use of employes such as the Mechanic-in-Charge. Rule 127 from the Agreement reads:





It is also noted that the Organization challenged the practicality of the Carrier's having not sent two carmen from Green Bay as opposed to transporting two separate employes from two separate points. The assignment of employes so long as it is consistent with the Agreement is clearly within the prerogatives of the Carrier. Therefore, the Board will make no finding on this point.










Attest
        Nancy J. -Executive Secretary


Dated at Chicago, Illinois, this 20th day of June, 1984