·l
Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 10290
SECOND DIVISION Docket No. 10142
2-NRPC-MA-'85
The Second Division consisted of the regular members and in
addition Referee Eckehard Muessig when award was rendered.
( International Association of Machinists and Aerospace Workers
Parties to Dispute:
( National Railroad Passenger Corporation
Dispute: Claim of Employes:
1. That the Carrier improperly suspended Machinist W. Howie (hereinafter
referred to as Claimant) on October 31, 1981, and subsequently dismissed
him on November 10, 1981.
2. That the Carrier be ordered to restore Claimant to service and compensate
him for all wage loss from date of suspension to date of restoration to
service.
2. That the Carrier violated handling procedures as set forth in Rule 24
(d).
Findings:
The Second Division of the Adjustment Board, upon the whole record and all
the evidence finds that:
The carrier or carriers and the employe or employes involved in this dispute
are respectively carrier and employes within the meaning of the Railway Labor Act
as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
This claim arose after the Carrier found the Claimant guilty to a charge
that he had refused a direct order from one of its Foremen to work on a locomotive.
The Carrier relied upon the testimony of its officials at the investigative hearing
to arrive at its finding of a rule violation.
In its appeal, the Organization essentially contends that the Claimant did
not refuse to comply with a direct order, since at the time he was in the process
of discussing grievance procedures with co-workers. It provides extensive arguments
and
contentions to
conclude that the testimony at the hearing was both confusing
and contradictory and, therefore, does not lead to a substantive finding of guilt
to the charges. Moreover, it also argues on procedural grounds, contending,
among other things, that a violation of Rule 24 (d) has occurred "since your
office did not reply to the appeal with the time limit as per agreement".
Form 1 Award No. 10290
Page 2 Locket No. 10142
2-NRPC-MA-185
With respect to the procedural contentions of the Organization, the record
shows that the Claimant was dismissed from the service effective November 11,
1981. The initial appeal, on both procedural and substantive grounds, was filed
on December 4, 1981. The parties met in conference on December 18, 1981, during
which the Claimant's dismissal was discussed.
On
January 7, 1982, the Carrier
denied the claim. It followed that on February 4, 1982, the former General Chairman
appealed the dismissal to the Director of Labor Relations of Amtrak. Letters of
inquiry concerning the status of the case were sent by the Organization on April 14
and May 17, 1982, since no reply had been received to the February 4, 1982 letter.
In its May 17 letter, the Organization raised the Rule 24(d) time limit issue
previously cited. The next significant event occurred on June 30, 1982 at which
time the parties held a conference to again discuss the claim under dispute. On
July 22, 1982, the Organization sent a status inquiry letter, noting that it had
not received a decision to its appeal as a result of the June 30, 1982 conference,
although almost a month had passed. At this time, it reiterated its earlier
position with respect to the Rule 24(d) time limit contention.
On July
29, 1982, the Carrier again denied the claim on both substantive and
procedural grounds. On the latter, it contended that Rule 24(d) required that an
appeal decision must be rendered within 30 calendar days of a conference. It
argued that the Rule does not obligate the Carrier to answer a claim within 30
days of the appeal, as contended by the Organization.
Certainly, under reasonable standards, the Organization had a right to expect
an earlier reply to its appeal of February 4, 1982. Moreover, the Rule doe's
require "a conference on the appeal". However, the Rule is silent with respect to
the parties' responsibility to schedule a conference. The Carrier contends, and
provides substance to its contention, that it had been the practice of the parties
to hold an appeal in abeyance pending a conference to be scheduled at a mutually
agreeable time and date, in essence, contending that it is a shared responsibility,
with respect to the scheduling of the conference. Therefore, the argument flows
that the 30-day time limit does not begin until the conference is held. Accordingly,
while we do not condone the Carrier's laxness in responding to the appeal and,
after full consideration of the Organization's well-stated argument in the record
and before the Board, we do not find a procedural violation, given the relevant:
facts and circumstances, herein.
Concerning the substances of the charge, three officials essentially testified
that the Claimant refused a direct order of his Supervisor. Moreover, the Claimant
acknowledged that he refused a direct order. While perhaps the Claimant's Supervisor
might have been more sympathetic to the Claimant's desire to be helpful to his
co-workers, the Supervisor's actions are not shown as unreasonable ones. The
Claimant has a basic responsibility to respond to a legitimate order. In the
incident here, after first being asked to do the work, he refused; he then had
other opportunities to comply, he still refused. By so doing, he placed himself
at peril to the consequences of his actions.
Form 1 Award No. 10290
Page 3 Locket No. 10142
2-NRPC-MA-185
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest: _ '00 '00ee"
Nancy J er - Executive Secretary
Dated at Chicago, Illinois, this 27th day of February 1985.