Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 10383
SECOND DIVISION Locket No. 10173
2-BN-CM-185
The Second Division consisted of the regular members and in
addition Referee Peter R. Meyers when award was rendered.
( Brotherhood Railway Carmen of the United States and Canada
Parties to Dispute:
( Burlington Northern Railway Company

Dispute: Claim of Employes:






















Findings:

The Second Division of the Adjustment Board, upon the whole record and all the evidence finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.


Form 1 Award No. 10383 _

Page 2 Locket No. 10173
2-BN-CM-185

On December 4, 1981, Carrier changed the work week at its Superior repair facility from a six-day week with Saturday-Sunday and Sunday-Monday rest days, to a seven-day week with Monday-Tuesday and Wednesday-Thursday rest days. Additionally, the Carrier abolished the Carmen's second shift, effective December 4, 1981. A time claim was filed on behalf of the Claimants, seeking eight-hours' compensation for each Claimant at the time and one-half rate for each Sunday worked, and eighthours' compensation at straight-time for each Claimant's first rest day in their new assignments.

The Organization contends that the Carrier's schedule change violates Rules 1(a)-(d), 1(g), 4, 6, 8, and Appendix K of the current Agreement, all governing the work week and wage scales.












Form 1 Award No. 10383
Page 3 Locket No. 10173
2-BN-CM-185











































Form 1 Award No. 10383
Page 4 Locket No. 10173
2-BN-CM-185

The Organization argues that because a seven-day work week was never in effect at the Superior facility before this change, the aforementioned rules limit the Carrier to a deviation only from a Monday-Friday week to a Tuesday-Saturday week.

The Organization argues, in addition, that any backlog of cars that existed prior to this change was the result of a massive layoff of Carmen that took place between August and December 1981. In other words, the Organization contends that the Carrier has failed to show that an operational problem arose that could not be met by a six-day work week.

The Carrier contends that there is no contract provision that prevents it from staggering work assignments through the week to cover seven-day service requirements. The Carrier maintains that there is a bona fide need for staggered assignments, as evidenced by the fact that repair work has always taken place on Sunday at the Superior facility; prior to December 4, 1981, this work was done on an overtime basis on Sundays, at additional expense to the Carrier.

The Carrier further argues that because repair work is required seven days per week and because the Agreement does not prevent such a scheduling change, the Carrier was under no obligation to confer with the employees in order to reach an agreement about the work schedule before implementing it.

Finally, the Carrier argues that there is no basis to award the damages sought by Claimants, even if the claim has merit. The Carrier maintains that the Claimants have already received straight-time pay for any Sundays worked; also, the claim for eight-hours' pay for the first rest day of the new assignments constitutes a double penalty.

This Board has reviewed all of the arguments and evidence in this case, and it finds that at the time in question, there is no doubt that the Superior facility was a six-day operation. Moreover, it has been established that prior to going to a seven-day operation, Carmen were called in for overtime on weekends, and many declined and had their names removed from the overtime list. Consequently, the Carrier was unable to meet the demands of its customers. There was a continuing backlog problem of cars needing repairs, and the only solution for the Carrier was to go to a seven-day week. In the language of Rule 1, the "Railway Company's operational requirements" had required that the Carrier "stagger" the work week; it was no longer "practicable" to have the days off be Saturday and Sunday.

Although the Organization contends that the backlog of cars was a direct result of the massive layoffs which had taken place prior to the move to a sevenday operation, this Board does not have enough evidence before it to support that assertion. The burden of proof is on the Organization. Even so, it is still evident from the record that the work was just not getting done, and the Carrier needed a seven-day operation in order to meet the needs of its customers.

Finally, it is clear that Rule 1(g) is not applicable to the six-day operation, such as the one at hand, since it refers simply to deviations from the regular Monday-Friday work week. Hence, absent an agreement between the Railroad and the

General Chairman, the Carrier can implement the new work schedule.
Form 1 Award No. 10383
Page 5 Locket No. 10173
2-BN-CM-185

As has been stated many times, except insofar as it might be restricted by the Collective Bargaining Agreement and limited by law, the assignment of work necessary for its operations lies within the Carrier's discretion. It is the function of good management to arrange the work within the limitations of the Agreement and in the interest of efficiency and economy. (See Second Division Award 5331.)

The Organization claims that the Carrier had no right to abolish the second shift and then claim that it needed a seven-day work week to get the work done. However, the issue of the abolition of the second shift is not before this Board at this time. We, therefore, are unable to rule upon it.

This Board has reviewed the language of Second Division Award 8289, submitted by the Organization, as well as the Dissent by the Carrier Members, and concludesthat in the case at hand, the Carrier had the authority under the Agreement to change from a six-day to a seven-day operation. Nothing in the language of the Agreement precludes it, and we are bound by that Agreement.








Attest: _ . _
      -NNancy J. v -Executive Secretary


Dated at Chicago, Illinois, this 24th day of April 1985.