Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 10388
SECOND DIVISION Docket No. 10494
2-ICG-SMW-185
(Sheet Metal Workers'
International Association
Parties to Dispute:
(Illinois Central Gulf Railroad Company
Dispute: Claim of Employes:
1. That the Carrier violated the current agreement, established practice,
provisions and rules of the Sheet Metal Workers' Section "B" Agreement when the
Carrier failed and refused to give proper and sufficient notice to Sheet Metal
Worker Water Service Repairman, J. R. Sholar when they abolished his position
on March 28, 1983.
2. That the Carrier be ordered to additionally compensate Sheet Metal
Worker, J.R. Sholar in the amount of 32 hours at the pro rata rate for the time
lost due to the improper advance written notice of at least five (5) working
days from April 4 through April 8 before the abolishment of his position.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to Organization in ex parte
form, hearing thereon was waived, and the Division is now in receipt of a
request from the Carrier that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest: _
ancy J. v -Executive Secretary
Dated at Chicago, Illinois, this 1st day of May 1985.