Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 10531
SECOND DIVISION Locket No. 10649
2-SP-MA-'85
The Second Division consisted of the regular members and in
addition Referee Raymazd E. McAlpin when award was rendered.
( International Association of Machinists and Aerospace
( Workers
Parties to Dispute:
( Southern Pacific Transportation Company
Dispute: Claim of Employes:
1. That the Carrier improperly suspended Leslie S. Lewis (hereinafter
referred to as Claimant) from service on April 10, 1983 to and
including April 21, 1983, a period of ten (10) days.
2. That, accordingly, the Carrier be ordered to rescind
suspension
and
compensate Claimant for all wage loss resulting therefrom.
Fin din gs
The Second Division of the Adjustment Board, upon the whole record and
all the evidence finds that
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The Claimant, Leslie S. Lewis, was given a ten day actual suspension as
a result of an investigation conducted on March 4, 1983. The Claimant was a
machinist assigned to the Carrier's Ogden Shop and in service for a period of
twelve years.
The Claimant is charged with failure to properly carry out his assignment, specifically, the failure of wick lubricators on Unit 8384, which
caused the Carrier to replace two of six wheel assemblies at a cost of
$7,200.00. The Claimant had signed the Carrier's form indicating that the
unit was ready to be placed in service.
Form 1 Award No. 10531
Page 2 Docket No. 10649
2-SP-MA-'85
The Organization argued that the failures occurred 25 days after
the work was performed and the unit had completed numerous trips and it could
have been tampered with. It further argued that the Carrier's procedures
were defective and that the turnover report indicated that the work had been
completed. The Carrier responded that the turnover report stated that the
wick units were set in. There was no indication that the bolts had not been
properly torqued. The Carrier further noted that the Claimant signed for the
work and if the bolts had been properly torqued, they would not have fallen
out, causing the damage to the unit. The organization countered that the
failure of the unit cannot be directly tied to the Claimant's work, and that
the Claimant was the victim of poor instructions by his Supervisor. Finally,
the Carrier argued that the penalty was appropriate in this case, had this
defect not been caught at the Carrier's Los Angeles inspection point, it
could have resulted in a derailment.
The Claimant is charged with a serious dereliction of duty. It is
his responsibility to check the work for which he has signed. Therefore, the
Board, after careful review of the evidence presented, finds that the investigation was properly held and no evidence was presented that would allow the
Board to substitute its judgment for that of the Carrier. The record does
contain substantial evidence to support the charge and the discipline
assessed is reasonable in light of that proven charge.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
Nancy er - Executive Secretary
Dated at Chicago, Illinois, this 4th day of September 1985.