Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 105451
SECOND DIVISION Docket No. 10316
2-B&O-CM-'85
The Second Division consisted of the regular members and in
addition Referee Robert W. McAllister when award was rendered.
( Brotherhood Railway Carmen of the
( United States and Canada
Parties to Dispute:
( The Baltimore and Ohio Railroad Company
Dispute: Claim of Employes:
1. That the Baltimore and Ohio Railroad Company violated the controlling
agreement, when on the date of March 4, 1982, the Willard assigned wrecking
crew was deprived of performing wrecking work at a location known as Lester,
Ohio.
The Willard,
Ohio
assigned wrecking crew was relieved at this
derailment prior to completion of the required wrecking service, and outside
contractors and equipment, void any Carrier assigned
wrecking crew,
was
allowed to
continue wrecking
work at this derailment, performing wrecking
service work which accrued specifically to the Willard assigned wrecking
crew, by virtue of the provisions or Rule 142 and 142-1/2 of the controlling
agreement.
2. That accordingly, Carrier be ordered to compensate Claimants, (a11
members of the Willard assigned wrecking crew), for all losses suffered
account Carrier's violation of the above referred to Agreement rules.
Claimants are as follows: F. W. Long, R. C. Cavalier, G. K. Colich, L. E.
Masterson and E. W. Bannaworth; claiming four (4) and one-half hours, each
Claimant, at the double time rate of pay.
FINDINGS:
The Second Division of the Adjustment Board, upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
On March 4, 1982, a derailment occurred at Lester, Ohio. The Carrier
called and assigned the Willard Wrecking Crew to the derailment. They arrived
at 3:30 A.M. Thereafter, the Carrier called two outside crane rental
companies, and they arrived at 7:00 P. M., March 4. While setting up for the
work, the Carrier sent the Willard wrecking crew back to Willard, Ohio, to
work on a derailment within the yard. The six Claimants are members of the
Willard Wrecking crew who were relieved at 3:00 A.M. The remaining Members
worked to clear the yard derailment.
Form 1 Award No. 10549 -
Page 2 Locket No. 10316
2-B&O-CM-'85
The Organization argues the Carrier's actions violated the provisions of
Rule 142-1/2, which reads as follows:
p1. When pursuant to rules or practices, a Carrier utilizes
equipment of a contractor (with or without forces) for the
performance of wrecking service, a sufficient number of the
Carrier's assigned wrecking crew, if reasonably accessible to the
wreck, will be called (with or without the Carrier's wrecking
equipment and its operators) to work with the contractor. The
contractor's ground forces will not be used, however, unless all
available and reasonably accessible members of the assigned
wrecking crew are called. The number of employes assigned to the
Carrier's wrecking crew for purposes of this rule will be the
number assigned as of the date of this Agreement.
Note: In determining whether the Carrier's assigned wrecking
crew is reasonably accessible to the wreck, it will be
assumed that the groundmen of the wrecking crew are called at
approximately the same time as the contractor is instructed
to proceed to the work.
2. This rule modifies existing rules only to the extent
specifically provided herein."
The Carrier initially points out that, one of the Claimants requested
and received personal leave on March 5. It is the Carrier's position that,
after he was relieved at 3:00 A.M.,he was no longer available for duty.
Our review of the record affirms the Carrier utilized the equipment of a
contractor to perform wrecking work. The Williard wrecking crew was already
at the scene when these outside cranes arrived. Consequently, no issue of
accessibility has been raised. The contractor's ground forces were used, but
all available members of the wrecking crew were not.
The Carrier's submission acknowledges a settlement of one hour's pay at
the straight time rate was offered on the basis the rerailings started up
again at Lester at 7:00 A.M., one hour prior to the start of the Claimants'
tour of duty for March 5, 1982. The Carrier considers the Organization's
claim excessive and without support for the punitive rate. Through prior
awards, this Board has affirmed that, when a contract violation is found, the
appropriate rate of compensation for work not performed is at the pro rata,
straight time rate.
NOW
Form 1 Award No. 10549
Page 3 Docket No. 10316
2-B&O-CM-'85
With respect to Claimant Cavalier, the Board notes the claim does not
involve work beginning on March 5. Rather, the claim is for those hours
following the release of the Claimants at 3:00 A.M. which was contiguous with
the prior work date, March 4. In accordance with these findings, we will
sustain the claim only to the extent of the pro rata, straight time rate.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest.
Nancy J yer - Executive Secretary
Dated at Chicago, Illinois, this 18th day of September, 1984