Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 10652
SECOND DIVISION Docket No. 10113
2-B&O-CM-'85
The Second Division consisted of the regular members and in
addition Referee Eckehard Muessig when award was rendered.
( Brotherhood Railway Carmen of the United States
( and Canada
Parties to Dispute:
( Baltimore and Ohio Railroad Company
Dispute: Claim of Employes:
1. That the Baltimore and Ohio Railroad Company violated the controlling agreement, specifically Rule 142 and 142 1/2 when they
called two outside contractors with their equipment and ground
forces, to perform wrecking service at Tipp City, Ohio on
October 18, 1981 in lieu of the Cincinnati, Ohio assigned wrecking crew.
2. That the Baltimore and Ohio Railroad Company be ordered to compensate the members of the Cincinnati, Ohio assigned wrecking
crew as follows:
R. L. Frey, L. Salmons, A. Mackey, J. C. Smith and J. Whitford
in the amount of seven (7) hours and twenty (20) minutes pay
each at the time and one-half rate.
J. Burdsall, C. Lambert, T. Risdon and L. Robinson, Jr., in the
amount of six (6) hours and fifty (50) minutes pay each at the time
and one-half rate.
Findings:
The Second Division of the Adjustment Board, upon the whole record and
all the evidence finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
This dispute concerns the claim of the Organization that the Cincinnati,
Ohio assigned Wrecking Crew should have been called for work on October 18,
1981, for a derailment.
The record shows that, on October 18, 1981, Train 4088 derailed two cars
outside of Tipp City, Ohio. To assist in rerailing the cars, the Carrier
called three Carmen and a Foreman from Dayton, Ohio and two additional Carmen
and a Foreman from Lima, Ohio. The Carrier also called two Contractors,
Form 1 Award No. 10652
Page 2 Docket No. 10113
2-B&O-CM-'85
Isringhausen Wrecking Service and Hulcher Emergency Service, who supplied an
80-ton mobile crane, two sidebooms and a front-end loader. The Contractors
low
furnished a total of six employees. It is the assignment of work to the
Contractors which has triggered this dispute.
The Organization contends, pursuant to Rule 142 1/2 of the Shop Crafts
Agreement, that the members of the Cincinnati, Ohio assigned Wrecking Crew
based approximately sixty (60) miles from the scene of the derailment in
question should have been called. It asserts that the Claimants were
available and reasonably accessible for the work in dispute, as contemplated
by the controlling rule. It particularly cites and relies upon Second
Division Award 8444 in support of its contention that the claim should be
allowed in its entirety.
In consideration of the total record before us, we find that the evidence
is clear that a sufficient number of the Carrier's assigned Wrecking Crew at
Cincinnati, Ohio were reasonably accessible on October 18, 1981, to perform
the work here. Therefore, there was unquestionably lost work opportunity to
the Claimants in the decision to use outside forces to perform work which is
reserved to them by the Agreement (although the parties are not in agreement
as to the exact number of hours). Accordingly, since the Agreement here does
not contain provisions to make an award as advanced by the Organization, we
follow the long line of awards and Court Decisions that the breach of the
contract, under the facts and circumstances here, entitled the wronged party
only to compensation for any harm he may have suffered. We are also guided by
the general thrust of decided cases on the property under comparable
situations, particularly Second Division Awards 8766, 9014, 9091, 9712 and
9887 with respect to the rate of pay. Moreover, while the Board is not -
unmindful of Second Division Award 9014 concerning its holding that compen
sation was due for Contractor time "actually on site", here we do not find the
facts and circumstances leading to that award precisely on point in this
matter. Accordingly, after a complete review and consideration of all of the
contentions and submissions of both parties, we embrace the pro rata rate
concept, having been established that this is the measure of work lost.
Therefore, in applying the make whole principle, we hold that the Claimants
will be awarded compensation at the straight time rate of pay.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest.
Nancy J er - Executive Secretary
Dated at Chicago, Illinois, this 20th day of
November
1985.