Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 10653
SECOND DIVISION Docket No. 10155
2-B&O-CM-'85
The Second Division consisted of the regular members and in
addition Referee Eckehard Muessig when award was rendered.
( Brotherhood Railway Carmen of the United States
( and Canada
Parties to Dispute:
( The Baltimore and Ohio Railroad Company

Dispute: Claim of Employes:












Findings:

The Second Division of the Adjustment Board, upon the whole record and all the evidence finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



At approximately 6:15 P.M. on October 29, 1981, Train District Run, Engine 3890 derailed five cars at Troy, Ohio. The Carrier called Hulcher Emergency Service from Mercer, Pennsylvania, located approximately 236 road miles from Troy. The Carrier states that the Contractor arrived at the derailment at 3:30 A.M. October 30, 1981, commenced working at 4:35 A.M. and was relieved at 9:30 A.M. that same date.

The Organization contends, and Carrier does not refute, that the Contractor's work force consisted of eight (8) men. The Organization asserts that the Contractor was relieved at 9:45 A.M., not 9:30 A.M., as contended by the Carrier.


Form 1 Award No. 10653
Page 2 Docket No. 10155
2-B&0-CM-'85

This dispute is controlled by the interpretation and application of Rule 142 1/2, which reads:























The record sets forth that an "assigned wrecking crew" had been established at Cincinnati, Ohio. The Board, on the record before it, also finds that a sufficient number of the Cincinnati wrecking crew was available and reasonably accessible to the wreck. Accordingly, the issue remaining is the amount of compensation, if any, due the Claimants.

There was unquestionably lost work opportunity to the Claimants in the decision to use outside forces to perform work which is reserved to them by the Agreement (although the parties are not in agreement as to the exact number of hours). Accordingly, since the Agreement here does not contain provisions to make an award as advanced by the Organization, we follow the long line of awards and Court decisions that the breach of the contract, under the facts and circumstances here, entitles the wronged party to the amount it would have earned if the breach had not occurred. We are also guided by the general thrust of decided cases on the property under comparable situations, particularly Second Division Awards 8766, 9014, 9091, 9712 and 9887, with respect to the rate of pay. Moreover, while the Board is not unmindful of Second Division Award No. 9014 concerning that part of its holding that compensation was due for Contractor time "actually on site", here we do not find the facts and circumstances precisely on point in this matter. Accordingly, after a complete review and consideration of all the contentions and submissions of both parties, we embrace the pro rata rate concept, having been established that this is the measure of work lost. Applying the make whole principle, we conclude from the record that the Contractor was called at
Form 1 Award No. 10653
Page 3 Docket No. 10155
2-B&O-CM-'85

approximately 8:00 P.M. on October 29, 1981 and finished at 9:30 A.M., on October 30, 1981, a total of thirteen (13) and one-half hours. In view of the foregoing, we sustain the claim as to the number of hours claimed for each Claimant at the straight time rate, less time worked by each of the Claimants during the period of time used here for this Award (8:00 P.M. on October 29; 9:30 A.M. on October 30, 1981).



    Claim sustained in accordance with the Findings.


                            NATIONAL RAILROAD ADJUSTMENT BOARD

                            By Order of Second Division


Attest:
        Nancy J. I~er - Executive Secretary


Dated at Chicago, Illinois, this 20th day of November 1985.
j Tt

INW