NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 10744
SECOND DIVISION Docket No. 10565
The Second Division consisted of the regular members and in
addition Referee Paul C. Carter when award was rendered.
(Brotherhood Railway Carmen of the United States
( and Canada
Parties to Dispute:
(Soo Line Railroad Company
Dispute: Claim of Employes:
1. That under the current agreement, the Soo Line Railroad Company
is in violation of Rules 27, 28 and 98 of Shops Craft Agreement, when
effective at 6:00 p.m., March 10, 1982 and thereafter to March 12, 1982, when
derailment site at Auburndale, WI was cleaned up, the Soo Line Railroad
Company allowed the outside contractor's equipment, with eight (8) operators
and two ground men, to perform the Carmen's work after the emergency ceased,
to clean up the derailment site.
2. That accordingly, the Soo Line Railroad Company be ordered to pay
Carmen D. Behnke, G. Molski, E. Walkush, N. Sankey, A. Kielpenski, H.
Kolpinski and J. Klicinski, Stevens Point, WI, assigned wrecker crew members,
150 hours at straight time to be divided equally among the claimants for loss
of compensation of pay they could have earned when the Soo Line Railroad
Company secured the services of the outside contractor's equipment and ten
(10) of its employes.
FINDINGS:
The Second Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board had jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The record shows that about 4:00 A.M., March 9, 1982., thirty-four
freight cars derailed on Carrier's main line at Auburndale, Wisconsin.
Carrier's Wrecking Crew located at Stevens Point, Wisconsin, performed ground
work at the site of the derailment, while outside contractors forces cleared
the site, which included moving twenty-four cars, that had been destroyed and
sold to a private contractor for disposal, to a location that was a safe
distance from the track. The Carrier states that due to the time likely to be
consumed in transferring potash loads from each of the twenty-four 130-ton
capacity cars that were destroyed, a 1,400 feet long temporary track, referred
to in the record as a "shoo-fly track," was built around the wreck site.
Traffic over the "shoo-fly" track was restricted to ten miles per hour. The
Form 1 Award No. 10744
Page 2 Docket No. 10565
2-S00-CM-'86
"shoo-fly" track was placed in operation at 5:00 P.M., March 10, 1982. The _
potash loads were not completely transferred until March 13, and the main line
was not placed back into operation until 3:10 P.M., March 22, 1982.
The Organization does not dispute the right of the Carrier to use
outside equipment and operators as long as an emergency existed, but contends
that the emergency ceased to exist when the "shoo-fly" was installed.
The Organization cites Rules 27, 28 and 98 of the Agreement. Those
rules are set forth in the record, and we see no necessity for repeating them
here, except we point out that rule 98 - 3(a) recognizes that in the case of
an emergency the Carrier may use the equipment of a contractor (with or
without operators), and a sufficient number of the regularly assigned Wrecking
Crew located at the nearest point to the scene of the wreck will be called to
work with the contractor as groundmen. The Employes recognize that an
emergency existed from March 8, 1982, through 6:00 P.M., March 10, 1982.
The Carrier points out that the Claimants herein, assigned members of
the Stevens Point Wrecking Crew, were used at the derailment site on March 10,
11, and 12, 1982, the dates involved in the Claim, and each was compensated
for eight hours or more, some up to 17.5 hours, for each day of the Claim.
The Carrier also points out that the Wrecking Crew members worked at the site
on March 16, 17, 18 and 19, 1982, loading trucks from the derailed cars onto
flat cars and securing wrecked cars to flat cars.
The Carrier contended on the property and contends before the Board
that the construction of the "shoo-fly" did not return the main line
operations to normal, and also that the cleanup work required the moving of
cars farther from the track than was possible by the use of Carrier's
equipment, and that the use of contractors' equipment for this work was
necessary.
The Board agrees that the Carrier had the right under the existing
situation at Auborndale during the period involved in the Claim, to determine
the need for contractors' equipment. We have been referred to prior Awards of
this Board, Nos. 6757, 7979, 8395, 8235, all involving the use of outside
contractor forces to assist in derailment situations on this Carrier, and also
Award No. 10111 which involved the Carrier's use of employes other than Carmen
to rerail a Car within the Roundhouse area.
On the basis of the facts in this case, and considering precedent
Awards on the same Carrier, the Claim herein will be denied.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest
Nancy J
OK
- Executive Secretary
Dated at Chicago, Illinois, this 19th day of February 1986.