Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 10805
SECOND DIVISION Docket No. 10771-T
2-SSR-MA-'86
The Second Division consisted of the regular members and in
addition Referee Peter R. Meyers when award was rendered.
(International Association of Machinists and Aerospace
( Workers
Parties to Dispute:
(Seaboard System Railroad
Dispute: Claim of Employes:
1. That the Seaboard System Railroad (formerly Seaboard Coast Line
Railroad) violated the current and controlling Agreement, dated January 1,
1968, particularly Rules 51 and 26, but not limited thereto, when they
misassigned Machinists' work of setting up brakes and testing locomotives for
outbound service at Rocky Mount, North Carolina, on May 7, 1983 to an
electrician and a hostler.
2. That accordingly, Machinist L. F. Melvin who was available to
perform the misassigned Machinist' work on May 7, 1983, be compensated in
amount of eight hours pay at the overtime rate.
FINDINGS:
The Second Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Claimant L. F. Melvin is employed as a Machinist by the Carrier,
Seaboard System Railroad. As of April 22, 1983, a Machinist no longer was
regularly assigned to the Carrier's Rocky Mount, North Carolina, Engine House
on Saturdays. On Saturday, May 7, 1983, the Rocky Mount Engine House Foreman
sent an Electrician and a Hostler to the South Rocky Mount train yard to cut
an engine from one train, put it on another, and test it to go out. The
organization filed a Claim on the Claimant's behalf, charging that the
Claimant was available and should have been assigned the work that instead was
assigned to the Hostler on May 7, 1983.
The Organization contends that the Carrier violated the Controlling
Agreement, particularly, but not limited to, Rules 51 and 26, when it
reassigned the Rocky Mount Machinist position so that no Machinist was on duty
on Saturdays, and then assigned an Electrician and a Hostler to do Machinists'
work on May 7, 1983.Rule 51 provides:
Form 1 Award No. 10805
Page 2 Docket No. 10771-T
2-SSR-MA-'86
"(a) Machinists work shall consist of laying out,
fitting, adjusting, shaping, boring, slotting,
milling and grinding of metals used in
building, assembling, maintaining,
dismantling, and installing locomotives and
engines (operated by steam or other power)
. . . ; engine inspection, air equipment;
. . . the operation of all machines used in
such work."
Rule 26 provides:
"(a) None but mechanics or apprentices regularly
employed as such shall do mechanics' work as
per special rules of each craft, except
foremen at points where no mechanics are
employed.
(b) This rule does not prohibit foremen in the
exercise of their duties to perform work.
(c) At points where there is not sufficient work
to justify employing a mechanic of each craft,
the mechanic or mechanics employed at such
points will, so far as they are capable of
doing so, perform the work of any craft that
it may be necessary to have performed.
(d) Helpers when used in any way in connection
with mechanics' work shall in all cases work
under the orders of the mechanic, both under
the direction of the Foreman."
The Organization argues that the disputed work - - setting up brakes
and mechanically testing locomotives for outbound service - - has been
recognized system-wide as Machinists' work under the Agreement, custom, and
past practice. The Organization asserts that the Agreement does not allow the
Carrier to assign Hostlers and Electricians to perform and/or assist in
Machinists' work; Hostlers have never performed the disputed work at any point
in the Carrier system where Machinists are assigned and available to perform
the work.
The Organization argues that the Carrier cannot simply blank the
Machinists' job and transfer the work to Electricians and Hostlers; the
Carrier misassigned the disputed work on May 7, 1983. The Organization
therefore contends that the Claim should be sustained in its entirety: the
Claimant should be compensated in the amount of eight hours' pay at the
overtime rate, and in the future, a Machinist should be made available to
perform all Machinists' work at Rocky Mount, North Carolina.
Form 1 Award No. 10805
Page 3 Docket No. 10771-T
2-SSR-MA-'86
The Carrier contends that the Organization has not established that
the disputed work is reserved for Machinists under the Controlling Agreement
or past practice. No inspection of the locomotive at issue was required, nor
was an inspection form completed in this case. Checking brake operation on
outbound locomotives is not reserved to any craft by either Agreement or past
practice. The Carrier further points out that Rule 51 makes no reference
either to testing brakes or to coupling or uncoupling locomotives; in fact,
other crafts' Agreements specifically include this type of work. The Carrier
argues, therefore, that the disputed work does not belong to the Machinists'
craft either by Agreement or by past practice.
The Carrier finally argues that any of its fundamental rights that
are neither specifically limited nor abridged by the Controlling Agreement are
reserved for the Carrier's free exercise. The Carrier asserts that it is
free, therefore, to assign its employees and run its business in any legal
manner.
The Carrier therefore contends that there has been no violation of
the Agreement, and this Claim should be denied in its entirety.
It is fundamental that absent an express reference to the disputed
work in the Classification of Work Rule, an Organization bears the burden of
proof to demonstrate that the disputed work has historically, customarily,
traditionally, and exclusively been performed by the craft which is claiming
it. In this case, the Machinists must demonstrate conclusively that the
coupling and uncoupling of locomotives and the testing of brakes is
exclusively and traditionally Machinists' work. See Awards Nos. 9236, and
7174.
This Board has reviewed all of the evidence in this case, and it
finds that there is no evidence in the record to substantiate the
Organization's claim that the disputed work has been performed by Machinists
to the exclusion of others. On the contrary, there is sufficient evidence
that Hostlers, Hostler Helpers, Engineers, and Electricians all perform the
work claimed by the Machinists in this case. Hence, there is not sufficient
evidence for the Board to find the work exclusively belongs to the Machinists
and that the Carrier violated the agreement. See Award No. 10051.
As we have stated in the past, except insofar as it is restricted by
the Collective Bargaining Agreement or limited by law, the assignment of work
necessary for its operations lies within the Carrier's discretion. See Award
No. 1777. In this case, there are no such restrictions or limitations as
claimed by the Organization; and therefore the Claim must be denied.
Form 1 Award No. 10805
Page 4 Docket No. 10771-T
2-SSR-MA-'86
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
Nancy J. eorr - Executive Secretary
Dated at Chicago, Illinois, this 2nd day of April 1986.