Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 11268
SECOND DIVISION Docket No. 11297
2-NRPC-MA-'87
The Second Division consisted of the regular members and in
addition Referee Paul C. Carter when award was rendered.
(International Association of Machinists
( and Aerospace Workers
Parties to Dispute:
(National Railroad Passenger Corporation
Dispute: Claim of Employes:
1. The National Railroad Passenger Corporation, (Amtrak) violated Rule 24
of the schedule Agreement effective September 1, 1977, but not limited thereto, when it arbitrarily and capriciously disciplined Machinist R. Richter by
assessing him a ninety (90) day, (60 actual, 30 deferred) suspension as a
result of investigation held October 30, 1985.
2. Accordingly, Machinist R. Richter should be made whole for all losses
resulting from the discipline with seniority unimpaired and all rights and
benefits restored and his record cleared of any reference to the charge.
FINDINGS:
The Second Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon..
Without passing upon the procedural issues raised, the Board finds
that discipline was warranted against the Claimant. The discipline imposed by
the Carrier was not arbitrary, capricious or in bad faith. The Claim will be
denied.
A W A R D
Claim denied.
Form 1 Award No. 11268
Page 2 Docket No. 11297
2-NRPC-MA-'87
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
01
Attest: _
Nancy J. - Executive Secretary
Dated at Chicago, Illinois, this 20th day of May 1987.