Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 11352
SECOND DIVISION Docket No. 11142
2-BN-CM-'87
The Second Division consisted of the regular members and in
addition Referee Elliott H. Goldstein when award was rendered.
(Brotherhood Railway Carmen of the United States
( and Canada
Parties to Dispute:
(Burlington Northern Railroad Company
Dispute: Claim of Employes: _
1. That the Burlington Northern Railroad Company knowingly and willfully violated the provisions of the current controlling Agreement when they
failed to assign carmen to assist contractors at a derailment.
2. That Carmen G. Whalen, H. Heilman, M. Cain, S. Nickens, D. Dixon
and A. Bilkey be compensated for a total time of thirty-eight and five tenths
(38.5) hours each, at the time and one-half rate of pay.
FINDINGS:
The Second Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
On August 11, 1984, four cars were derailed at Carrier's Lindenwood
Yards, St. Louis, Missouri. At 11:00 P.M. Elliot Crane Service, Inc. was
called to rerail the cars. Two RC60 cranes arrived; each crane had one operator and one groundman. The cranes were used for ten hours and 45 minutes,
with the rerailing being completed at 11:45 A.M. In addition, L & E Railroad
Services furnished a 977 Caterpillar with two groundmen, arriving at 5:00
A.M., so that they worked a total of six hours and 45 minutes.
The Organization contends that Carrier violated Agreement Rule 86 (b)
and (c) when it utilized outside contractors to perform wrecking service on
the date in question. The Rules provide as follows:
Form 1 Award No. 11352
Page 2 Docket No. 11142
2-BN-CM-'87
"Rule 86. WRECKING CREWS
(b) When wrecking crews are called for wrecks
or derailments outside of yard limits, the regular
ly assigned crew will either accompany the outfit
or will be transported by other means to and from
the location of the wreck or derailment. For
wrecks or derailments within the yard limits,
sufficient carmen will be called to perform the
work.
(c) In the event other than company-owned
equipment is used for wrecks or derailments out
side yard limits, sufficient carmen from the
nearest location will be called to perform ground
service (not operating) with the other than company
owned equipment. The number of carmen called will
be sufficient when it equals or exceeds the number
of groundmen used by the outside firm."
The Organization contends, and we agree, that Carrier violated
Agreement Rule 86 (b) and (c) when it utilized outside contractors to perform,
wrecking service on the date in question. In this case four groundmen were
used - two for Elliot Crane Service totaling 21 hours and 30 minutes, and two
for L & T Railroad Services totaling 13 hours and 30 minutes, for a total
number of 35 hours.
At issue here is whether all the named Claimants were available to
perform the service, and if so, whether a Claim at the time and one half rate
is proper. After careful review of the record in its entirety, we find that
three of the Claimants were not available to be called, and, therefore, their
Claims must be denied. Car-man Heilman was on vacation starting August 13,
1984. Thus, August 12, the date the work was performed, was a rest day immediately preceding his vacation. Similarly, Claimant Nickens was on vacation
from July 30 to August 10, 1984, so that August 12 was a rest day immediately
succeeding his vacation. Neither has specified in writing pursuant to Rule 8
(c) that they desired to avail themselves of overtime calls on that date.
Accordingly, Carmen Heilman and Nickens failed to comply with Rule 8 (c) and
are not proper Claimants.
Claimant Bilkey was working vacation relief at Centralia, Illinois
during the period August 4 through 26, 1984, and was also unavailable for
service. Though he contended that he would be home on the weekend, since he
was assigned at another point, he was not available for overtime at St. Louis.
The remaining three Claimants, Whalen, Cain and Dixon, are entitled
to pay for the time worked by the outside firm's groundsmen. Two Claimants
are entitled to ten hours and 45 minutes each, and one is entitled to pay for
six hours and 45 minutes. We note that the Organization Claim for time and
one-half for service not performed is not supported by prior Awards of this
Division. (See Second Division Award Nos. 10010, 10153 and 10488). Accordingly, the straight time rate, and not the overtime rate, shall apply.
Form 1 Award No. 11352
Page 3 Docket No. 11142
2-BN-CM-'87
A WAR D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
Nancy J. r - Executive Secretary
Dated at Chicago, Illinois, this 30th day of September 1987.