88-2-86-2-173


(International Association of Machinists ( and Aerospace Workers PARTIES TO DISPUTE: (CSX Trans., Inc.

                STATEMENT OF CLAIM: As shown in Docket No. 11358 and not repeated herein.


                FINDNGS: The Second Division of the Adjustment Board finds:


That the dispute was certified to the Second Division of the Adjustment Board ex pane by the petitioning party; and

Under date of January 29, 1988 and February 5, 1988 the petitioning parties addressed a formal communication to the Executive Secretary of the Second Division requesting withdrawal of this case from further consideration by the Division, which request is hereby granted.

                        A W A R D


        Claim withdrawn.


                                NATIONAL RAILROAD ADJUSTMENT B09RD

                                By Order of Second Division


Attest:
        Nancy J. 101L "r - Executive Secretary


Dated at Chicago, Illinois this 24th day of February 1988.