Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 11519
SECOND DIVISION Docket No. 11118
88-2-85-2-252
The Second Division consisted of the regular members and in
addition Referee Hyman Cohen when award was rendered.
(Brotherhood Railway Carmen of the United States
( and Canada
PARTIES TO DISPUTE:
(The Seaboard System Railroad Company
STATEMENT OF CLAIM:
1. That the Seaboard System Railroad Company, hereinafter referred to
as the Carrier, was in violation of the Agreement, particularly Rule 30(a) and
Appendices B and C, when Foreman R. Bean repaired the wall of caboose 6244 on
September 19, 1984. Evansville, Indiana.
2. And accordingly, the Carrier should be ordered to additionally
compensate Carman I. Knight, hereinafter referred to as the Claimant, for two
(2) hours and forty (40) minutes pay at time and one-half rate as the result
of said violation.
FINDINGS:
The Second Division of the Adjustment Board upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
As Train Extra 8034 South arrived of the Carrier's facility at Howard
Yards, Evansville, Indiana, the inbound crew reported that a panel of the wall
of caboose 6244 was loose. A Car Foreman instructed a Car Inspector by radio
to report to the caboose upon completion of his "roll-by" inspection of the
inbound train. As the Carman approached the caboose, he was informed by
the Foreman that he was no longer needed. Since the Car Inspector was close
to the caboose, he entered the caboose to find the Foreman with a hammer in
his hand and the wall panel was secure. The Carrier's version of the facts is
that the Foreman proceeded to the caboose carrying with him a hammer and some
nails. Upon entering the caboose he observed that the condition of the wall
panel was beyond the repair capabilities of the trainyard car inspectors, but
Form 1 Award No. 11519
Page 2 Docket No. 11118
88-2-85-2-252
was safe for continued service to its destination without the need for repair.
The Foreman then drove four (4) nails into the caboose ceiling in front of the
wall panel. Although he believed that the wall panel was secure, it did not
appear to be
so.
He drove the nails into the caboose ceiling to lessen any
concern which may have been felt by the crew.
After carefully examining the record this Board finds that the work
performed by the Foreman rightfully belongs to Carmen as provided in Rules 30
and 104 of the Agreement. Since the work in question was not assigned to the
Howell Shop, the work should have been performed by Carmen, as required by
Rule 104. Although the Carrier invokes the de minimus rule inasmuch as it
claims that the work took only "a matter of minutes", it would have taken a
Carman more than a "a matter of minutes" to engage in an inspection and determine what was needed to make the caboose safe to continue and to obtain the
necessary tools to perform the actual work. Moreover, the position of the
Carrier that the work performed by the Foreman was for "cosmetic purposes"
rather than for the purpose of performing "repair or necessary work" is seriously undermined since he went to the caboose with a hammer and nails. By doing so this Board concludes that he had the intention of making repairs.
The Claimant was first out on the overtime board and was available
and qualified to perform the work in question. Consistent with Second Division Award No. 10642, in applying the make-whole principle, the Claimant is to
be awarded compensation at the straight time rate of pay rather than the rate
of time and one-half.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest: _
Nancy J ver - Executive Secretary
Dated at Chicago, Illinois, this 3rd day of August 1988.