Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 11613
SECOND DIVISION Docket No. 11468-T
88-2-87-2-109
The Second Division consisted of the regular members and in
addition Referee Raymond E. McAlpin when award was rendered.
(International Brotherhood of Electrical Workers
PARTIES TO DISPUTE:
(Soo Line Railroad Company

STATEMENT OF CLAIM:

1. That the Soo Line Railroad Company violated the current agreement, particularly Rule 2, when it assigned Electronic Engineer G. A. King, and Telex personnel, on April 16, 17, 18, 20, 21, 22, 23, and 24, 1986 to perform repair and maintenance work on the communications switchboard on the nineteenth floor of the Soo Line Building.

2. That accordingly, the Soo Line Railroad Company should be ordered to compensate the Claimant, M. A. Kahl, for thirty-six (36) hours at the rate: of time and one-half.

FINDINGS:

The Second Division of the Adjustment Board upon the whole record and all the evidence, finds that':

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



The Organization claimed a violation of Rule #2 when the Carrier assigned the Supervisory Engineer and an outside contractor to repair and test a switchboard at the Carrier's Soo Line building located in Minneapolis, Minnesota. Rule #2 is reproduced below:




Form 1 Award No. 11613
Page 2 Docket No. 11468-T
88-2-87-2-109












lost opportunity for work, the claim of 36 hours at time and one-half is appro
priate, and the Organization cited a number of awards to bolster their position.
The Organization noted their members are now doing the work and, therefore, the
Carrier concedes that the work belongs to the International Brotherhood of Elec
trical Workers members. Since it is undisputed on the property that a supervisor
performed the work, the Organization claimed its claim should be upheld in its
entirety.

The Board noted that the ARASA was notified for a response to the matter in this docket. The Organization declined to intervene and file a submission as noted in their response dated January 12, 1988.

The Carrier argued that the IBEW members are supervised by an electronic engineer. The work was corrective testing on a new system and new installation that was installed initially by the contractor which was the Telex Corporation. The Carrier argued that the supervisor may assist the contractor to work out the problems from the original installation. The Soo Line is obligated by contract with Telex, and the Carrier noted the Organization's members assisted where applicable. The Carrier further contended that its employees had no expertise in order to correct this problem and, in any event, the work is not exclusive to the IBEW. The Carrier stated that, through its Exhibit A, it gave notice on February 13, 1986 in accordance with Article II of the September 25, 1964 Agreement that it intended to subcontract the work in question; and since the Organization did not respond within ten days, the Carrier had the right to subcontract the work.

The Board finds that Rule #2 cited above placed the testing of all communication switchboards under the jurisdiction of the Organization. There is no showing that any other organization could claim this work under their scope rule. The Carrier raised arguments with respect to Article II - Subcontracting, which is part of the September 25, 1964 Agreement. This Agreement provides for the right to subcontract work when skilled manpower or essential equipment is not available on the property. It is apparent from the record that the type of work in question, that is the troubleshooting of the new switchboard installation, was outside of the skill level of the IBEW members that the Carrier had available to it. The Carrier argued that in accordance with this Agreement, they informed the General Chairman of the pending subcontract at which time the Organization would have ten days in which to respond. This letter was dated February 13, 1986. What the Carrier fails to note is that the work referred to

in the letter was on a new switchboard located at the Miller Davis Building. -
Form 1 Award No. 11613
Page 3 Docket No. 11468-T
88-2-87-2-109

The work in question in this docket is work that was performed at the Soo Line Building. Therefore, the Carrier fails in its contention that the Organization was properly informed of the subcontract as required in Article II of the 1964 Agreement. Contractual agreements between the Carrier and their subcontractor do not offer a valid defense to a Controlling Agreement violation. Since the work properly belongs to the Organization unless proper notice was given, the Organization will prevail in their claim. However the Board feels the appropriate remedy would be 36 hours to the Claimant at the pro rata rate.






                        By Order of Second Division


Attest:
        ancy J. _P- Executive Secretary


Dated at Chicago, Illinois, this 7th day of December 1988.