89-2-89-2-52


(Brotherhood Railway Carmen/ A Division of TCU
PARTIES TO DISPUTE:
(Chicago and North Western Transportation Company

STATEMENT OF CLAIM: As shown in Docket No. 11764 and not repeated
herein.

FINDINGS: The Second Division of the Adjustment Board finds:

That the dispute was certified to the Second Division of the Adjustment Board ex parte by the petitioning party; and

        Under date of June 16, 1989, the petitioning party adddressed a

formal communication to the Executive Secretary of the Second Division _,
requesting withdrawal of this case from further consideration by the Division,
which request is hereby granted.

                        A W A R D


        Claim withdrawn.


                              NATIONAL RAILROAD ADJUSTMENT BOARD

                              By Order of Second Division


Attest:
        Nancy J. w~r - Executive Sec etary


Dated at Chicago, Illinois, this 12th day of July 1989.