89-2-89-2-40


(International Brotherhood of Electrical Workers PARTIES TO DISPUTE: (Burlington Northern Railroad Company

                STATEMENT OF CLAIM: As shown in Docket No. 11773-T and not repeated herein.


                FINDINGS: The Second Division of the Adjustment Board finds:


That the dispute was certified to the Second Division of the Adjustment Board ex parte by the petitioning party; and

Under date of July 26, 1989 the petitioning party addressed a formal communication to the Executive Secretary of the Second Division requesting withdrawal of this case from further consideration by the Division, which request is hereby granted.

                        A W A R D


        Claim withdrawn.


                              NATIONAL RAILROAD ADJUSTMENT BOARD

                              By Order of Second Division


Attest.
        anc~ ever - Executive Secretary


Dated at Chicago, Illinois this 9th day of August 1989.