Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 11892
SECOND DIVISION Docket No. 11688
90-2-88-2-231
The Second Division consisted of the regular members and in
addition Referee Donald E. Prover when award was rendered.
(International Association of Machinists and
( Aerospace Workers
PARTIES TO DISPUTE
:
(Michigan-Wisconsin Transportation Company
STATEMENT OF CLAIM:
1. That, under the current Agreement, the Michigan-Wisconsin Transportation Company (former C&0 Railway Company) unjustly suspended Machinist
Jack Gerbers for a period of thirty days actual suspension March 28, 1988
through April 26, 1988, and a sixty-day record suspension.
2. That, accordingly, the Michigan-Wisconsin Transportation Company
compensate Machinist Jack Gerbers thirty days' pay at the pro-rata rate of pay,
in effect, beginning March 28, 1988 through April 26, 1988, and all other
benefits attached to his employment; and that the sixty (60) day record suspension be removed immediately and his record cleared.
FINDINGS:
The Second Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
As the result of a formal Investigation held on February 2, 1988, the.
Claimant was assessed a thirty (30) day actual suspension and a sixty (60) day
record suspension for allegedly tampering with the air monitoring equipment
aboard the Steamer Sparton on November 30, 1987.
Form 1 Award No. 11892
Page 2 Docket No. 11688
90-2-88-2-231
A review of the Investigation transcript indicates that no substantial evidence was produced that proved that Claimant was guilty of the charge..
The Carrier admits the evidence contained in the record is largely circumstantial. The Carrier's main argument is that Claimant could have been in a post-tion to tamper with the equipment. While Claimant had access to the monitoring equipment, so did several other individuals. None of the witnesses
testified that they observed Claimant tampering with the equipment and no motive for Claimant's alleged action was introduced at the Investigation.
That portion of the Claim requesting pay for the thirty day suspension has been settled by another tribunal, leaving only the matter of the
sixty day record suspension to be decided by this Board.
Based on the foregoing, the sixty day record suspension shall be
removed from the Claimant's record.
A W A R D
Claim sustained in accordance with the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
01
Attest:
Nancy J.ve r - Executive Secretary
Dated at Chicago, Illinois, this 18th day of July 1990.