Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 11936
SECOND DIVISION Docket No. 11684-I
90-2-88-2-171
The Second Division consisted of the regular members and in
addition Referee John C. Fletcher when award was rendered.
(G. W. Darnell & D. G. Pendleton, P. K. Stewart
PARTIES TO DISPUTE:
(Norfolk and Western Railway Company
STATEMENT OF CLAIM:
Claim of Carmen G. W. Darnell, D. G. Pendleton and P. K. Stewart that
the carrier violated the controlling agreement, and in particular Rule 30,
when they allowed apprentices, upon completion of their respective apprenticeship, to back date their journeyman seniority date ahead of claimants on
the seniority roster; and accordingly, the carrier be ordered to adjust the
seniority roster wherein the apprentices would have the same seniority date as
claimants, but be placed just below them on said roster. Roanoke, VA N & W.
FINDINGS:
The Second Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
Claimants, journeyman Carmen, contend that the collective bargaining
Agreement was violated when certain employees, upon completion of their Carman
apprenticeship, were placed above them on the seniority roster. At the center
of their complaint is the application of the July 10, 1980, Memorandum of
Agreement on Apprenticeship Training. This Agreement provides that upon
completion of a supervised training program, apprentices and helpers would be
given 732 days retroactive seniority. The retroactive seniority feature could
not be used to establish a date ahead of any journeyman employed on July 10,
1980. This proscription, though, by published interpretation, did not protect:
Carmen transferring from one point to another.
Form 1 Award No. 11936
Page 2 Docket No. 11684-I
90-2-88-1-171
Between September 1, 1982 and October 26, 1982, five apprentices
completed their training at Shaffers Crossing. All were granted 732 days
retroactive seniority. This placed them ahead of Claimants who, when furloughed at Shaffers Crossing in early 1975, transferred to Roanoke Shops. In
September 1975, Claimants were recalled at Shaffers Crossing, but declined,
opting instead to remain at Roanoke. This resulted in a forfeiture of their
Shaffers Crossing point seniority. In 1982 Claimants were furloughed at
Roanoke. They displaced at Shaffers Crossing and established new seniority
dates of August 2, 1982 at that point.
Carrier contends that the Claim is procedurally defective as well as
lacking in merit. We agree on both points. There is no question that the
time limits of the applicable Agreement were breached in the progression of
this matter to the Board. However, what is perhaps more critical, is that
the Claim is completely lacking in merit. From our review, the seniority
provisions of the collective bargaining Agreement, the terms of the July 10,
1980 apprenticeship Agreement and the accepted interpretation were correctly
applied in this instance. The fact that Claimants are displeased with this
correct application does not vest this Board with authority to order modifications.
A WAR D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
Nanc Dever - Executive Secretary
Dated at Chicago, Illinois, this 28th day of November 1990.
CARRIER MEMBERS' DISSENT
~. TO
AWARDS 12122 - 12130, DOCKETS 11905, 11913, 11914,
11934, 11936, 11990, 12037, 12116, 12117
(Referee Fletcher)
In 1986, the Contracting Parties entered into a National
Agreement providing for a specific rate of pay for those involved
in Intermodal Service. The purpose for negotiating such a
provision was to enable the railroads to compete with trucks and
other modes of transportation handling Intermodal traffic. It was
never the intent of the contracting parties that such ability to
compete with other modes of transportation would fluctuate on a day
to day basis but was to provide a level and stable platform from
which the railroads could confront the other transportation modes.
In these cases, the Majority has correctly found that Barstow,
California, one of nine locations on this railroad performing
Intermodal work, was covered by Section 1(b) of Article IV of the
November 19, 1986 Agreement. All of the Claimants held positions
that were engaged in work in connection with Intermodal equipment
and they had been compensated in accordance with Section 2 of
Article IV almost two years prior to the filing of the first case
here involving December, 1988. The majority also properly
concluded that the language, "preponderantly engaged" does not,
"limit employees such as Claimants to work exclusively in
connection with intermodal service."
The only issue in these cases was:
"...at what point is the Carman no longer working on
a position 'preponderantly engaged in work in
connection with the operation of intermodal facilities.'"
While the Majority states as a fact that:
"The Agreement gives us no guidance..."
as to how to evaluate "preponderantly engaged" it has nevertheless
concluded that such is to be done on a daily basis. This
conclusion is wrong for the following reasons.
First, as noted above, there is NO CONTRACTUAL BASIS for such
a conclusion. The positions involved were bulletined and were
awarded as INTERMODAL POSITIONS having a regular five day work
week. As the Majority has noted, "Unless it is demonstrated the
work on a particular intermodal position is not somewhat
consistent..." (Emphasis added), said position is an intermodal
position compensated at the intermodal rate. Therefore, in order
to assert entitlement to other than the intermodal rate, it must be
demonstrated that the work of a position is sufficiently erratic to
warrant it NOT being included under the rubric of "preponderantly
engaged." In these cases there is no evidence of any position
being shown as being such an erratic position that it was not
entitled to be identified as an intermodal position.
Furthermore, the Majority's conclusion that, "when more than
half the work day... is spent in connection with intermodal
service," identifies an intermodal position, does severe violence
to the concept of assigning positions by bulletin in this industry.
One example will prove the point. An intermodal worker who spends
3 1/2 hours each work day of his assignment in other than
intermodal service is an intermodal worker since, "more than half
the work day" is in intermodal service. However, an individual who
- 2 -
spends the same amount of time on non-intermodal work but only on
Monday and Tuesday of the work week is not an intermodal worker on
two days of his work week. The same time, effort and work .is
expended, yet there are two different results. Such is not what
the Parties intended and such action certainly does not provide a
stable means to compete against the other modes of transportation.
Secondly, on the assumption that these nine claims represent
the actual incidence of intermodal workers performing non
intermodal work at this location, we have a total of 51 dates
consuming 587 hours, 40 minutes in just over 48 weeks (December 12,
1988 - November 14, 1989 - 240 work days). If just one Carman
worked 3 1/2 hours each work day during these same 48 weeks in non
_ intermodal work he would have expended 840 hours in non-intermodal
f work for which he would be compensated only at the intermodal rate.
It just does not make any rational sense that an individual could
work 43% more than the total represented in these nine claims on
non-intermodal work and be within the guidelines of these Awards.
Yet, these multiple Claimants working far less hours in non
intermodal work are found here to be entitled to the other than
intermodal rate.
In Award 12122, involving the largest number of Claimants
(13), the largest number of dates claimed (18) and the most time
(290 hours) over a six week period (December 12, 1988 - January 20,
1989) we find that the 290 hours claimed is less that 16$ of the
time worked by these Claimants (13 Claimants x 8 hours x 18 dates
= 1872 hours). If we look at the time worked by these same 13
- 3 -
Claimants over the six week claim period (13 Claimants x 8 hours x
5 days/week x 6 weeks = 3120 hours) the total claimed is less than
10%-of the time worked. By any calculation, other than on a daily
basis, it is self-evident that Claimants were "preponderantly
engaged" in intermodal work and were so engaged not just the
majority of the time but the vast majority of time employed. Had
the Parties desired to require that the determination of the status
of the position being intermodal or not to be made on a daily basis
it would have been a simple matter to have so stipulated. However,
as the Majority has properly noted, there is no Agreement provision
that supports such a conclusion.
Third, the Majority itself has noted the lack of contractual
basis for making daily determinations-when it acknowledges the need
to provide an exception:
"The Board recognizes that there may be circumstances,
due to factors such as traffic patterns, when it is
appropriate to measure the work over a somewhat longer
period of time, e.g., a work week."
Obviously, the recognition, "that there may be circumstances"
in which a daily determination would not apply, upholds and
confirms the fact that there is no contractual provision to support
the conclusion reached in these Awards. Furthermore, what are the
traffic patterns that would entitle the Carrier to, "measure the
work over a .somewhat longer period of time..."? What other
circumstances might be "appropriate"? To acknowledge the need for
exceptions warrants the conclusion that an evaluation on a daily
basis was not the intent of the Parties in negotiating Article IV.
The result made in this matter is a disposition made on perceived
equity and not on any contractual support.
In Award 16 of PLB 4170, involving the application of the
intermodal rate, we find the following:
"If Claimants' positions are not primarily in
intermodal service, they are not subject to Article IV.
In resolving this dispute, we can consider only the
evidence presented to us. The Carrier has furnished a
computer generated report for the fourth quarter of
1988 which shows the number of man hours charged to
various functions for each intermodal employee at Inman
Yard. According to this report, Claimant Bailey worked
479.7 hours in intermodal equipment repair and 28.3
hours in shop maintenance. Claimant Tatum worked 388.7.
hours in intermodal equipment repair and 8.8 hours in
ship maintenance .... The Organization, on the other
hand, has submitted bulletins describing the jobs in
question. Because maintaining pig cranes is only one
of three duties listed on the bulletin, the
organization concludes this work constitutes only onethird of the job. In light of .the Carrier's more
precise time records, we cannot accept the
organizations's conclusion. Based upon the Carrier's
records, it is evident that Claimants' jobs are
primarily in intermodal service." (Emphasis added)
Here, the review was over a thirteen week period; not daily.
Again, there is no support either in Article IV of the
November 19, 1986 Agreement or in Letter No. 3 for the conclusion
that bulletined and assigned Intermodal positions are to be
reevaluated and reclassified on a daily basis.
The majority, in support of its conclusion has noted that this
Board historically, "...has examined the nature of an employee's
work on a daily basis" and that there is nothing in the 1986
Agreement that would change that view. However, such a conclusion
can only be reached if the basic purpose of the Intermodal
provisions are ignored. No railroad can compete with other less
costly transportation modes when its ability to compete is
restricted by an artificially imposed barrier.
The Majority also relies on rules 20 and 38 to support its
position of daily review. However, Rule 20 applies.to the rate of
pay for the filling of vacancies and there is no dispute that these
cases DO NOT INVOLVE THE FILLING OF A VACANCY. It is a fact of
record that the Claimants were assigned at the time to intermodal
positions by bulletin and assignment. There was no issue raised
concerning the filling of vacancies. And certainly there is no
dispute that Claimants properly could be required to perform nonintermodal work so long as they were "preponderantly engaged" in
intermodal work. Thus, there were no other positions nor were
there any vacancies to be filled. Concerning Rule 38, it was NEVER
raised on the property but was first raised by the Organization in
. rrr~
their Submission to this Board. Even though such argument should
have been excluded as being in violation of this Board's Circular
No. 1, the fact is that the parties by agreement in that rule did
make a specific contract provision, detailing when and how there
would be a change in the rate paid for welding. The Majority has
noted the fact here that there is NO SUCH RULE PROVISION in Article
IV.
Finally, it was the Organization that asserted a violation of
Article IV on the property. Thus, it was the organization's burden
to prove with substantial evidence that the National Agreement
adopted on November 19, 1986, DID PROVIDE for the application of
the intermodal rate to be made on a daily basis. The Majority has
- 6 -
correctly concluded that the National Agreement DOES NOT contain
such a provision and in fact, the Agreement provides NO GUIDANCE in
this regard. The organization's claims should have been denied on
their failure to support their claims with evidence. Whatever the
Parties meant by the term "preponderantly engaged" it is clear on
these records that Claimants, at all times relevant, were
"preponderantly engaged" in intermodal service and it was
contractually proper to compensate them at the intermodal rate.
We dissent.
M. W. FINGE HUT *'~
A141
M. C. LESNIK
P. . VARGA
,/
L. HICKS
~E~.l O ST