Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 12407
SECOND DIVISION Docket No. 12053-T
92-2-90-2-167
The Second Division consisted of the regular members and in
addition Referee George S. Roukis when award was rendered.
(Brotherhood Railway Carmen/Division of TCU
PARTIES TO DISPUTE:
(Norfolk and Western Railway Company
STATEMENT OF CLAIM:
1. That the N&W Railway Company violated current agreements, Rule
7, 17, 30, 31 and 103 of the September 1, 1949 agreement, as subsequently
amended, when on June 9, 1989, June 12, 1989, June 13, 1989 and June 14, 1989,
the carrier used two Maintenance of Way utility carpenters to work in Planing
Mill Shop building, making, measuring and completing bulletin boards and
blocks used to block loads in cars, etc, which is now by rule and long standing practice at Roanoke East End Planing Mill Shop Carmen's work.
2. That because of such violation the Norfolk and Western Railway
Company be ordered to compensate Planing Mill Machine Hand D. A. Wiles, who
was available and had rights under the aforementioned rules and long standing
practice at Roanoke East End Shops Planing Mill the following amounts:
June 9, 1989 - Four (4) hours at time and one-half rate of pay.
June 12, 1989 - Eight (8) hours at time and one-half rate of pay.
June 13, 1989 - One (1) hour at time and one-half rate of pay.
June 14, 1989 - Two (2) hours at time and one-half rate of pay.
Total of fifteen (15) hours at time and one-half rate of pay.
FINDINGS:
The Second Division of the Adjustment Board upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employes within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Form 1 Award No. 12407
Page 2 Docket No. 12053-T
92-2-90-2-167
The Organization contends that when Carrier used Utility Carpenters
represented by the Brotherhood of Maintenance of Way Employes on June 9 and
14, 1989 to perform asserted Planing Mill Machine Hand work said work assignments violated Rules 7, 17, 30, 31 and 103 of the Organization's Agreement. The work involved building a 72" x 40" bulletin board on June 9, and
cutting a 2" x 2" x 60" block on June 14. Specifically, the Organization
maintains that since the Claimant holds Planing Mill Machine Hand rights and
was available on the second shift of the claimed date he should have been
assigned this work. It points out that Planing Mill Hands have performed this
work for over forty years and observes that only since 1989, has Carrier
directed Maintenance of Way Utility Carpenters to perform Planing Mill Machine
Hand and Planing Mill Carpenters work. It also asserts that the work in
question is generally recognized as Carmen's work.
The Organization submitted a signed statement by two former long term
employees attesting that said work was performed by Carmen in the Planing
Mill.
Carrier contends that the work performed was not related to the
remanufacture or repairs of freight cars or subsumed under the language of
Rule 103 reading, "and all other carpenter's work in shops and yards." It
asserts that the Organization is seeking exclusive rights to work which was
properly assigned to Maintenance of Way Utility Carpenters. Moreover, it
argues that notwithstanding Claimant holds Planing Mill Machine Hand rights
these rights do not give exclusivity to the operation of machinery which is
used to cut and shape wood. It observes that since the inception of the
Utility Carpenter positions in Roanoke Shops (March 9, 1984) employees holding
these positions have routinely used available wood-working equipment to
perform identical work. A "To Whom it May Concern" attestation statement
dated September 27, 1989 was submitted by the Utility Carpenters. It reads:
"We, as the undersigned Utility Carpenters, have on
numerous occasions used woodworking equipment such as
saws, routers and drill presses, in the Planing Mill
to construct shelves, boards, safety boards, etc. in
the Roanoke Shop facilities. The above mentioned
fixtures are attached to buildings."
The Brotherhood of Maintenance of Way Employes as a Third Party in
Interest filed a Submission with the Board. Succinctly stated, the Maintenance of Way Employes asserted that the work of constructing and mounting a
bulletin board and cutting wooden blocks in connection with the maintenance,
repair and/or remodeling of Carrier's shop facility at Roanoke is clearly the
type of work contemplated under their scope and work classification rules.- It
also contends that the Carmen failed to establish via past practice or clear
rule language that said work was protected under Rule 103 of the Carmen's
Agreement.
Form 1 Award No. 12407
Page 3 Docket No. 12053-7C
92-2-90-2-167
In considering this case the Board concurs with Carrier's position.
While there is a presumption that said work belongs to the Carmen as evidenced
by the attestation statements of the formerly employed long term employees,
there is no clear Agreement language vesting such work or a demonstration of
systemwide practice. There is also a presumption that at least since March,
1984 when the Utility Carpenter positions were created that said employees
performed this work in the Planing Mill Shop. The Utility Carpenters
September 27, 1989 attestation statement supports this observation. Since it
appears and there is no credible rebuttal evidence that these employees did
not concurrently perform this work prior to the abolishment of the Planing
Mill Machine Hand position on April 27, 1989, we cannot conclude that Carrier
violated the cited provisions of the Carmen's Agreement. The record is bereft:
of hard substantive affirming evidence.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest:
Nancy J. D_,r~ Executive Secretary
Dated at Chicago, Illinois, this 12th day of August 1992.