CORRECTED
NATIONAL RAILROAD ADJUSTMENT BOARD
Form 1 SECOND DIVISION Award No. 12486
Docket No. 12294
92-2-91-2-84
The Second Division consisted of the regular members and in
addition Referee Edward L. Suntrup when award was rendered.
(Brotherhood Railway Carmen/
(Division of TCU
PARTIES TO DISPUTE:
(CSX Transportation, Inc. (formerly
(the Chesapeake and Ohio Railway Company)
STATEMENT OF CLAIM:
1. That the Chesapeake & Ohio Railroad Company (CSX
Transportation, Inc.) (hereinafter referred to as "carrier")
violated the service rights of Painter K. Estep (hereinafter
referred to as "claimant") and the provisions of Rule 11, 32 and
154 of the controlling agreement when on April 22, 1989 the carrier
ignored the overtime board and worked ten (10) employes from an
outside concern to prepare the new paint facility for painting in
violation of the aforementioned agreement rate.
2. Accordingly, the claimant is entitled to be compensated
for twelve (12) hours at the applicable time and one-half rate for
said violation.
FINDINGS:
The Second Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved
in this dispute are respectively carrier and employe within the
meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over
the dispute involved herein.
Parties to said dispute waived right of appearance at hearing
thereon.
Form 1 Award No. 12486
Page 2 Docket No. 12294
92-2-91-2-84
,_fir
On May 15, 1989, a Claim was filed by the Local Chairman on
behalf of Claimant at the Carrier's Raceland Car Shop, Russell,
Kentucky. Allegation was that the Carrier violated Rules 11, 32,
and 154 of the Agreement when it hired an outside contractor "...on
second shift to prepare the new paint Booth for painting" on April
22, 1989. According to the Claim, it took ten men working twelve
hours each to do the work. The Claim was later changed to include
twenty Painters of the Carmen craft who were working at Raceland.
In denying the original Claim the Carrier states that it is
true that a contractor by the name of Mobile Pressure Cleaning had
been hired to remove the overspray on the Raceland Shop spray booth
and that this company had done this work for the Carrier on two
previous occasions. According to the Carrier, the work at bar
needs equipment which the Carrier does not possess. This is a
specialized highway truck with mounted equipment which produces a
water blast of "...ten thousand pounds per square inch." After the
overspray was removed on April 22, 1992, according to the Carrier,
Carmen Painters "...recoated the paint booth with W. B. Filmite."
Rules 11, 32 and 154 state the following, in pertinent part:
"Rule 11--Effective June 1, 1923.
(c) Record will be kept of overtime .,r~
worked and men called with the purpose in view
of distributing the overtime equally.
UNDERSTANDING--Effective July 1, 1948.
(3) There will be an overtime call list
(or call board) established for the respective
crafts or classes at the various shops or in
the various departments or subdepartments, as
may be agreed upon locally to meet service
requirements, preferably by employees who
volunteer for overtime service. Overtime call
board will be kept under lock and key
available to view of employes. Overtime call
list will be kept under lock and key and made
available to employes when necessary."
'Rule 32--(a) Effective November 1, 1964--None
but mechanics or apprentices regularly
employed as such shall do mechanics' work as
per the special rules of each craft except
foremen at points where no mechanics are
employed. However, craft work performed by
foremen or other supervisory employes employed
on a shift shall not in the aggregate exceed
20 hours a week for one shift, 40 hours a week
`r`
for two shifts, or 60 hours for all shifts."
Form 1 Award No. 12486
Page 3 Docket No. 12294
92-2-91-2-84
Rule 154--(a)
Carmen's work shall consist of building,
maintaining, dismantling (except all-wood
freight-train cars), painting, upholstering
and inspecting all passenger and freight cars,
both wood and steel, planing mill, cabinet and
bench carpenter work, pattern and flask making
and all other carpenter work in shops and
yards, except work generally recognized as
bridge and building department work: carmen's
work in building and repairing motor cars,
lever cars, hand cars and station trucks;
building, repairing and removing and applying
locomotive cabs, pilots, pilot beams, running
boards, foot and headlight boards, tender
frames and trucks; pipe and inspection work in
connection with air brake equipment on freight
cars: applying patented metal roofing;
operating punches and shears doing shaping and
forming; work done with hand forges and
heating torches in connection with carmen's
work: painting with brushes, varnishing,
surfacing, decorating, lettering, cutting of
stencils and removing paint (not including use
of sand blast machine or removing in vats);
all other work generally recognized as
painters' work under the supervision of the
locomotive and car departments, except the
application of blacking to fire and smoke
boxes of locomotives in engine houses; joint
car inspectors, car inspectors, safety
applicance and train car repairers;
oxyacetylene, thermit and electric welding on
work generally recognized as carmen's work;
and all other work generally recognized as
carmen's work.
(b) It is understood that present
practice in the performance of work between
the carmen and boilermakers will continue.
UNDERSTANDING--Negotiated February 9-22, 1922.
Paint spraying machines will be operated
by painters unless this practice is changed by
some ruling or interpretation from the Labor
Board."
Form 1 Award No. 12486
Page 4 Docket No. 12294
92-2-91-2-84
In response to the Carrier's denial at first level of
handling, the Local Chairman states the following:
"Contrary to your statement the Claimant could
and should have performed the work in
question. The Carrier has at its disposal
suitable methods of removing the build-up of
paint overspray from the paint booth
(sandblasting, scraping, chemical removal)
besides the use of high pressure water
blasting. Furthermore, the Carrier has at its
disposal the ability to procure the so-called
'specialized' water blast equipment at a
considerably cheaper cost than sub-contracting
this work."
The Organization further argues that removal of overspray paint
from paint booths is and always has been recognized as work covered
under the Classification of Work Rule that it normally and
traditionally was performed by Painters and this is the practice
throughout the system.
The Carrier's response to this line of argument by the
organization is that the contractor did not "prepare" the Paint
Booth for painting, but it cleaned the Paint Booth. The Carrier
states the following:
"The purpose of the work performed by Mobile
was not to prepare the paint booth for
painting, it was to clean the walls and
ceiling of the paint booth, not because it
needed painting, but because it needed
cleaning. As cars are painted automatically
in the paint booth the overspray accumulates
on the walls andceiling and if not removed,
the weight of the accumulation would cause it
to drop onto and ruin the finish of cars being
painted below. This cleaning process is not
work which its painters have done in the past,
and the carrier does not possess the necessary
equipment to do the cleaning. As Mr. Brigman
advised the Local Chairman, the cleaning
requires specialized equipment designed to
blast with a pressure of ten thousand pounds
per square inch. In addition, Mobile used
specialized equipment, which the Carrier does
not possess, which is necessary to collect the
used water with the overspray contaminants and
to dispose of it properly as required by the
Kentucky Environmental Protection Agency. ,___r
Form 1 Award No. 12486
Page 5 Docket No. 12294
92-2-91-2-84
The necessity of utilizing Mobile was not
because the paint booth needed painting, it
was because it needed cleaning. After the
paint booth had been water blasted, a coating,
called 'Filmite' is applied to the walls and
ceiling by Carrier's painters. The coating
causes the overspray to be more easily removed
by water blasting. Thus, it is the necessity
to clean the walls and ceiling which causes
the subsequent application of the coating. If
it were not necessary to clean the paint
booth, the Filmite would not need to be
replaced.
The Organization's contention that the Carrier
has other means of removing the overspray from
the paint booth, such as (sandblasting,
scraping, chemical removal), is ill-founded
and not supported by knowledge of the paint
facility and its operation. The Carrier
invested about $5 million to construct a
modern Paint Shop at Raceland. The design
concept did not include shutting down the
painting process for the extraordinary length
of time it would take to employ the antiquated
method of erecting scaffolding and placing men
thereon to scrape and chisel the overspray by
hand. It was designed to avoid the damage to
the walls and ceiling of the paint booth that
sand blasting would cause; and it was designed
to avoid the use of chemicals, which can
introduce new problems and expense relating to
safety and to proper disposal methods.
The methods suggested by your organization
would, understandably, be more labor
intensive; but in the exercise of its right to
manage its business prudently, the Carrier
does not have to employ more expensive
procedures when less expensive ones are
available so long as it is not restricted by
the Agreement with its employees."
The issue before the Board is whether the operant Rules cited
by the Organization cover the cleaning of the paint booth at
Raceland Shop, and more specifically, whether they cover the
cleaning of the technologically new type of booth which the Carrier
installed at large expense which needed a special process in order
to be prepared for the application of Filmite by the craft's
Painters.
Form 1 Award No. 12486
Page 6 Docket No. 12294
92-2-91-2-84
The Organization argues that preparing paint booths had been
traditionally done by the craft throughout the system. That is not
contested by the Carrier. What the Carrier contests is that the
new type of paint booth which it installed at Raceland had never
been "cleaned" by this craft and that to do so by the older methods
of sandblasting, scraping or chemical removal would not only be
potentially physically destructive to the new equipment, but that
the time it would take such labor intensive procedures to be used
would be unnecessary downtime of expensive equipment. The
argument, and distinction, that the Carrier makes between
"preparing" and "cleaning" the new booth is neither addressed nor
answered by the Organization on property. The Carrier argues that
the craft still did the "preparing" of the paint booth, as the
Claim requests, by applying Filmite.
Do the Rules cited by the Organization require the carrier to
use this craft to "clean" the new booth (in addition to applying
the Filmite preparation), with additional, expensive equipment
which it would have to purchase or lease, and then train members of
the craft to use such equipment which, practically speaking, would
be used infrequently? Examination of the language of the Rules at
bar indicates that, if there is a contractual imperative which
requires the Carrier to teach this craft to use -new machinery to
clean the new booths it would be found in Rule 154. That Rule
,__r
explicitly addresses the painting of passenger and freight cars,
painting with brushes, varnishing, surfacing, decorating and so on,
and it states that Carmen shall do "...all other work
generally recognized as painters' work under supervision of the
locomotive and car departments...:' Since the parties specifically
disagree over the application of this latter language to the
cleaning of the new paint booth, the Board must look to past
practice. There is none per se which supports the Claim since the
technology used to clean the booth is different than the old paint
removal technology. There is no evidence that the craft had ever
done this specific kind of work. Further, the Carrier notes that
this is the third time that it had contractors come in and do the
work at bar albeit the application of the Filmite, prior to the
re-use of the paint booth, remains Painters' work. Although the
Organization always has the privilege and right to police its
Agreement, it is undeniable that a past practice~had set in at this
shop by which the Carrier had cleaned the paint booth with
contractors.
low
Form 1 Award No. 12486
Page 7 Docket No. 12294
92-2-91-2-84
On balance, the Board must conclude that the Organization has
insufficiently met the burden of proof that the idiosyncratic, new
work of cleaning the new paint booth necessarily belongs to its
craft. For the craft to have prevailed in this case, the Carrier
would have had to initiate new training, with new equipment, to
handle new work, done quite infrequently, which had not been done
by the craft in the past. In short, neither the general language
of Rule 154, nor any identifiable past practice relative to the
kind of work specifically at bar in this case, supports the
position of the organization in this Claim and the Board must rule
accordingly.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest
ancy J 90er - Executive Secretary
Dated at Chicago, Illinois, this 18th day of November 1992.
-AIW