93-2-89-2-82


(International Association of (Machinists and Aerospace Workers PARTIES TO DISPUTE: (National Railroad Passenger Corporation

                  STATEMENT OF CLAIM: As shown in Docket 11794 and not repeated herein.


FINDINGS: The Second Division of the Adjustment Board finds:

That the dispute was certified to the Second Division of the Adjustment Board ex parte by the petitioning party; and

Under date of April 27, 1993, the petitioning party addressed a formal communication to the Executive Secretary of the Second Division requesting withdrawal of this case from further consideration by the Division which request is hereby granted.

                        A W A R D


          Claim withdrawn.


                          NATIONAL RAILROAD ADJUSTMENT BOARD

                          By Order of Second Division


ATTEST: _
      ancy J. D~- Secretary to the Board


Dated at Chicago, Illinois this 12th day of May 1993.