(International Association of Machinists &
(Aerospace Workers
PARTIES TO DISPUTE:
(Norfolk Southern Railway Company



FINDINGS: The Second Division of the Adjustment Board finds:

That the dispute was certified to the Second Division of the Adjustment Board ex parts by the petitioning party: and


Under date of February 22, 1994, a formal communication was addressed to the Interim Secretary of the Second Division requesting withdrawal of this case from further consideration by the Division which request is hereby granted.


                        A W A R D


            Claim withdrawn.


                            NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Second Division


Attest:
      Catherine Loughrin I terim Secretary to the Board


Dated at Chicago, Illinois this 6th day of April 1994.