Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD
SECOND DIVISION
Award No. 13302
Docket No. 13105
98-2-96-2-4

The Second Division consisted of the regular members and in addition Referee Eckehard Muessig when award was rendered.

(Brotherhood Railway Carmen, Division of ( Transportation Communications International Union PARTIES TO DISPUTE: (CSX Transportation, Inc. (former Louisville and ( Nashville Railroad Company)

STATEMENT OF CLAIM:











FINDINGS:

The Second Division of the Adjustment Board, upon the whole record and all the evidence, finds that:
Form 1 Award No. 13302
Page 2 Docket No. 13105


The carrier or carriers and the employee or employees involved in this dispute are respectively carrier and employee within the meaning of the Railway Labor Act, as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




On December 21, 1992, the Carrier's Mechanical Superintendent met with the Claimant and two Carmen Apprentices for the purpose of filling two Carmen vacancies at the Carrier's New Orleans, Louisiana, Car Shop. The Superintendent selected the two apprentices to fill the vacancies.


On March 12, 1993, the Local Chairman filed a claim asserting that the Claimant should have been selected to fill one of the vacancies. The Organization claimed that the Carrier violated a portion of Rule 118, Paragraph D which reads "after all carmen in good seniority standing at all points have been restored to service, in accordance with Rule 26, and additional carmen are needed, apprentices shall be handled in the following order." Here the Organization submits the Claimant had Agreement rights beyond the'. apprentices.


In its letter dated April 9, 1993, the Carrier denied the claim, because the Claimant did not follow the "established procedure for requesting a transfer" and because the Claimant did not have a good safety record.


On July 2, 1993, the Organization requested that the claim be paid because it had not received the Carrier's denial letter, dated April 9, until June 21, 1993, when it was hand delivered to the Organization. The Organization notes that the Carrier had 60 days from the time the claim was filed to deny it. In this case, because the Organization did not receive the denial letter until June 21 (well beyond the 60 days imposed by .agreement) the Carrier breeched the Agreement and. therefore, must pay the claim.


On July 14, 1993, the Carrier asserted to the Organization that it had mailed its denial letter on April 9. It provided a "screen print" that showed the date the letter was created to support its contention of having mailed the letter on April 9.

Form 1 Award No. 13302
Page 3 Docket No. 13105
98-2-96-2-4

By letter dated August 11, 1993, the Organization reiterated its position that the claim should be allowed because of the time limit violation.


The Carrier's response, dated October 1, 1993, again rejected the claim when it, in particular part, stated as follows:




Form 1 Award No. 13302
Page 4 Docket No. 13105



In its reply to the Carrier, dated April 14, 1994, the Organization, in pertinent part, stated:



Form 1 Award No. 13302
Page 5 Docket No. 13105
98-2-96-2-4



Following further correspondence on the property, the claim was progressed to the Board for resolution.

Based on the record developed on the property, the Board finds that the claim must be sustained because of procedural error by the Carrier on the property.

As a threshold procedural matter, the key issue is the proper construction of Article V - Carrier's Proposal No. 7, Paragraph (a) which reads as follows:

Form 1 Award No. 13302
Page 6 Docket No. 13105
98-2-96-2-4

The question is whether the Organization was "notified" in writing within the meaning of the above-cited Rule. Absent other conditions or explanations by either party, the Board concludes that "notify" as used in the above-cited Rule means "sent", i.e. that the Carrier's decision was dispatched. The Carrier provided no evidence of substance that it "sent" the denial letter. For example, no certified or registered mail receipt was introduced into evidence.


With respect to the question of damages, the Board concludes that this matter is best resolved by the payment of $1,179.65 to the Claimant as discussed by the parties during conference on December 13, 1995.




      Claim sustained in accordance with the Findings.


                        ORDER


This Board, after consideration of the dispute identified above, hereby orders that an award favorable to the Claimant(s) be made. The Carrier is ordered to make the Award effective on or before 30 days following the postmark date the Award is transmitted to the parties.


                        NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Second Division


                        Dated at Chicago, Illinois, this 6th day of August 1998.