(Brotherhood Railway Carmen Division

(Transportation Communications International Union PARTIES TO DISPUTE:
                  (I & M Rail Link, Inc.


                    STATEMENT OF CLAIM: As shown in Docket No. 13648 and not repeated herein.


                    FINDINGS: The Second Division of the Adjustment Board finds:


That the dispute was certified to the Second Division of the Adjustment Board ex parte by the petitioning party; and

Under date of January 27, 2003, the petitioning party addressed a formal communication to the Arbitration Assistant requesting withdrawal of this case from further consideration by the Division which request is hereby granted.

                        AWARD


      Claim withdrawn.


                      NATIONAL RAILROAD ADJUSTMENT BOARD

                      By Order of Second Division


Dated at Chicago, Illinois, this 28th day of February 2003.