NATIONAL ROAD ADJUSTMENT BOARD
(International Brotherhood of Electrical Workers
PARTIES TO DISPUTE: (
(Union Pacific Railroad Company
STATEMENT OF CLAIM: As shown in et No: 1not
repeated herein.
The Second Division of the Adjustment Board finds:
That the dispute was certified to the Second Division of the Adjustment Board ex
pane by the petitioning party; and
Under date of January 14, 20tkT the petitioning party addressed a formal
communication to the Arbitration Assistant requesting withdrawal of this case from
further consideration by the Division which request is hereby granted.
AWARD
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Dated at Chicago, Illinois, dais 6th day of August 2007.