PARTIES TO DISPUTE:
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
CHICAGO AND NORTH WESTERN RAILWAY COMPANY

STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood:


(1) That the Carrier violated the provisions of the effective agreement by assigning or permitting employes of Henry Danischefsky, General Contractor, to perform work necessary in connection with the extending of a concrete platform at the Milwaukee Passenger Station during the period December 2, 1946, to December 5, 1946, inclusive;


(2) That the following employes of the B&B Department be compensated at the pro rata rate for an amount of time equivalent to that required by the employes of the contracting company to perform the above mentioned work;









(3) That each employe referred to be paid for his proportionate share of the total time worked by the employes of Henry Danischefsky, General Contractor, during the period December 2, 1946, to December 6, 1946, inclusive.


NOTE: The Ennployes in their claim as set forth in their notice of intention to file specify the dates on which the contractor worked at Milwaukee Passenger Station as being December 2, 1946 to December 5, 1946, inclusive; but now have accepted the Carrier's dates of November 30 and December 2, 3, and 4, 1946, and therefore wish to correct the claim in this respect.


EMPLOYES' STATEMENT OF FACTS: During the period November 30 and December 2, 3, and 4, 1946 inclusive, the Carrier assigned or permitted employes of Henry Danischefsky, General Contractor, to perform work necessary in connection with the extending of a concrete platform at the Milwaukee Passenger Station. During the period involved, the Carrier bad, in its employment, approximately twelve B&B mechanics assigned to the territory of which the Milwaukee Passenger Station is a portion. Work of this nature and type has heretofore and subsequently been performed by B&B forces.


Agreement between the parties dated April 1, 1936, is by reference made a part of this Joint Statement of Facts.



4159-4 463

platform constructed in 1944 under a similar contract. The work in connection with the construction of the platform extension was performed by the employes of the contractor on November 30, December 2, 3 and 4, 1946. During the period involved the carrier had in its employ 12 bridge and building employes assigned to the territory that included Milwaukee, Wisconsin, all of whom were employed the full measure of their assigned working hours.


POSITION OF CARRIER: Work of the nature involved in connection with the construction of the extensin of the concrete platform at Milwaukee has, to a limited extent, been performed by employes of the carrier; however, new construction of this type has generally been handled by contract to outsiders better equipped to perform the work- As indicated above, the concrete platform to which the extension was made in 1946, was constructed by an outside contractor in 1944, There was no claim presented account that work being let to an outside contractor, neither was there any contention on the part of the employes or their authorized representatives that the performance of such work by employes of the contractor was in violation of the provisions of schedule rules agreement with the maintenance of way organization. The work of extending the platform at Milwaukee Passenger Station in 1946 was let to a contractor for the reason that the carrier's bridge and building forces could not handle that work and also adequately take care of the necessary regular maintenance requirements. The twelve bridge and building employes were not deprived of employment as a result of the construction of the concrete platform extension having been let to a contractor. All of those employes, with the exception of two who laid off account illness on December 2, 1946, worked full time during the period November 30 to December 4, 1946, inclusive. In fact. two of the men each worked overtime on two days during that period.


It is the position of the carrier that the claim should be denied for the following reasons:






OPINION OF BOARD: This is a companion case to Award 4158. The principles applicable to a decision of this case are the same as those expressed in the Opinion of the Board in the aforesaid award. WD view the construction of the extension of a platform at the Milwaukee Passenger Station in the same light as the construction of the concrete roadway involved in the previous case. This view is taken, however, only because of the special circumstances and surrounding facts in these two cases and is not intended as an indication that this Board feels that all new construction work 1s outside the Scope of the Agreement.


FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:


That the Carrier and the Employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act, as approved Tune 21, 1934;

4159-5 46.E

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein: and





    Claim denied.


              NATIONAL RAILROAD ADJUSTMENT BOARD

              By Order of Third Division


ATTEST: A. I. Tummon
Acting Secretary

Dated at Chicago, lllinois, this Sth day of November, 1948.