STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood:
(1) That the Carrier violated the agreement by not assigning to Section Foremen John Huff and Don Crawford and eleven Section Laborers to work of installing the drain tile on Millwood and Caneyville Sections, Kentucky Division, on May 30, 1945;
(2) That the above referred to claimants be reimbursed for all monetary loss suffered by them because of the Carrier's improper action.
JOINT STATEMENT OF FACTS: On May 30, 1945, Decoration Day, the claimants, Section Foremen and Laborers on the Millwood and Caneyville Sections of the Kentucky Division, performed no service for the railroad company. On that day, however, and for a period both prior and subsequent to May 30, 1945, Young and Greenawalt, contractors, Chicago, were engaged by the Carrier in the original installation of corrugated metal 8" pipe at sixty-nine (69) locations in four groups of drainage systems on the two sections. Millwood section is from mile posts 73 to 80, and C'aneyville is from mile posts 80 to 88. The installations varied in length from 17 to 118 feet, and their. depth from the base of the rail varied from 5 to 30 feet at locations shown hereafter:
5. That the Carrier's engineering staff did not possess the specialized training and experience required to plan and direct the work.
6. That the claimants did not possess the specialized training and experience necessary to perform the work.
7. That the work, being hazardous in nature, had to be performed by men especially trained to know and avoid those hazards.
8. That the work, consisting of the installation of four intrarelated systems of drainage units, could not be segregated to permit Carrier's employes to be integrated with contractor's forces in performing the work.
9. Claim is not based on any rule of the agreement, hence it is in effect a request for a new rule-which the Board does not have authority to grant.
12. It has been a practice of many years for Carrier to contract work of the character involved in this case.
13. Carrier is charged by law with operating efficiently and economically. The carrier is not in position to perform periodical work of this nature efficiently and economically.
OPINION OF BOARD: Carrier contracted outside the Organization 69 installations of drainage pipe, in depths from 5 feet to 30 feet, requiring 138 days for completion and costing $21,675.00. On Decoration Day, May 30th, 1945, Claimants performed no service for the Carrier, and claim here is predicated on their right to perform work on that day on that installation project.
The applicable principles have been repeatedly declared. As said in Award 4671, "Generally, it hardly needs to be said, the Carrier may not contract out work embraced within its collective agreements. However, those agreements deal with realities and are given a practicable construction, and it is recognized that wherever, without neglect of the Carrier in proper maintenance of its equipment and forces, it is required to perform a task of such magnitude or specialization or essential danger or time requirements, that it is not feasible for the Organization to furnish or procure the labor and skill or not feasible for the Carrier to furnish or procure the equipment for the adequate performance of the task, then the work may be contracted out."
Here the Carrier sets out, among other matters with supporting data, that drainage problems are reated to soil composition and condition and to geological formations and climate; that many technical procedures were required with use of special tools and devices, including trenching machines, not possessed by the Carrier; that speed in operation is essential to prevent earth movement; that the work was hazardous by nature; that the specialized necessary equipment would seldom be in use and required trained personnel in its operation, and that such work on that property has always, and over a long term of years, been performed by contractors specializing in such work. It relies particularly on a letter agreement appearing in the submission which we do not deem controlling here, and consequently shall not consider.
Without denial of the Carrier's statements, generally, except to state their opinion that the frequency of such work would justify the purchase of necessary equipment, the Committee contends that all these matters are irrelevant for the reason that their claim in the instant case does not concern the installation work as an entire task but only for the right to work on that job for the one day claimed at digging and baekfilling with picks and shovels. In the statement filed by the Employes at the hearing, it is said: 4 7 vs-l0 805
The question of the Carrier's right to contract out the entire drainage installation is not before us. Claimants have eliminated that issue. So assuming, we think the Carrier could not in reason be held to anticipate that on any particular day the contract work would require pick and shovel work of digging and filling, or- to arrange with the contractor for use of Carrier's laborers to perform work thereon for that particular day. We agree with the Carrier that the statement in Award 3206 is in point, that; "While it is asserted that the air compressor operator could have done the work performed by the Contractor's air-compressor man, we think that it would be rather difficult to divide the project into the small component parts; that the contract as a whole being outside the scope of the Agreement, it would neither be expedient nor wise to place small obstacles in the path of management and thus limit its discretion and judgment and cause friction and discord and perhaps the failure of the entire project."
FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and