NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood:
JOINT STATEMENT OF FACTS: On or about December 1, 1948, employes of Young and Greenwalt, drainage contractors, were assigned to place two tunnel liner plate culverts, each 54 inches in diameter by 96 feet in length, beneath the Carrier's tracks at Bridges S-95.5 and S-95.6. These bridges are located south and east of Fremont, Nebraska.
The culverts were placed in the embankment at new locations to replace 24 inch cast iron culvert pipes which were previously buried and abandoned and not removed after the new culverts were completed. The metal culverts, which were installed by the contractor's employes, consisted of metal rings 20 inches wide, each ring being cut into three sections. The culverts were placed beneath the embankment by excavating and tunneling, the excavating being done on the outer sides of the embankment, the tunneling being done directly beneath the center portion of the embankment.
After excavating or tunneling for approximately 2 feet, these additional sections to provide a 20 inch ring were bolted in place and this procedure repeated until the entire culverts were in place. The excavated material was removed through the installed pipe.
The agreement, dated January 1, 194?, between the two parties to this dispute, and subsequent amendments and interpretations are by reference made a part of this Statement of Facts.
POSITION OF EMPLOYES: During the handling of this claim on the Carrier's property, the Director of Personnel, Air. G. F. Stephens, addressed the following letter to the General Chairman, under date of June 4, 1949.
to have the work of installing the new pipe culverts at Bridges S-95.5 and S-95.6 taken care of as quickly as possible.
It is the position of the carrier that for the following reasons the claim herein involved is not justified and should be denied:
OPINION OF BOARD: This dispute falls in the general category of contract cases. The facts are agreed on and are recited in the joint submission above stated. Those facts, by reference, are made a part of this opinion.
As an abstract principle, a Carrier may not let out to others the performance of work of a type embraced within one of its agreements and, where exceptions to the scope of the agreement are claimed, other than those expressly mentioned, any other limitation upon the agreement must be established by definite proof. See Award 757.
On the facts at issue, the Board finds that the Carrier has failed to establish by definite proof in this case that the work in question is excepted from the scope of the agreement.
Contentions of the Carrier have failed to hold up under the close scrutiny of the Board and must fall one by one under the weight of the agreement, Board precedent and the facts of the case. For controlling authority compare Award 5090 and awards cited therein.
FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved Tune 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and