NATIONAL RAILROAD ADJUSTMENT BOARD

THIRD DIVISION




PARTIES TO DISPUTE:


STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood of Railroad Signalmen of America on the Southern Railway Company:






EMPLOYES' STATEMENT OF FACTS: Following the negotiation of rules, dated March 19, 1949, by a National Conference Committee establishing a shorter work week consisting of five eight-hour days, the Carrier placed into effect, as of September 1, 1949, the shorter work week.


Hourly paid employes on five-day positions were assigned Saturday and Sundays as their rest days, except that occupants of certain positions were improperly assigned Sundays and Mondays as their rest days.


The positions assigned rest days of Sundays and Mondays on the territory under the supervision of Mr. M. A. Otterbourg are shown in the bulletin reproduced herewith:












5545-1s 531

Division, National Railroad Adjustment Board has no authority to sustain the claim


For all of the reasons given, the claim should in all things be denied and the Carrier respectfully requsts that the Board so hold.




OPINION OF BOARD: We are called upon in this dispute to interpret the Forty-Hour Week rules for non-operating employes.


The Claimants challenge the Carrier's action in staggering the positions of signal maintainers and assistant signal maintainers at nine stations, and establishing for the employes there employed a work week from Tuesday through Saturday, with Sunday and Monday as rest days.


In essence, the position of the Employes is that the claimants are filling positions, the duties of which can reasonably be met in five days; that such positions are five-day positions coming within Rule 30(c)(I), and that the assigned work week should therefore have been Monday through Friday with Saturday and Sunday as rest days.


The Carrier's position briefly is that the positions in question are six day positions and that the work weeks in question were staggered in order to meet the Carrier's operational requirement.
















5545-19








The Employes argue that since signalmen now work five days a week, the positions are five-day positions under the agreement, and that in any event there is nothing about the work of signalmen that requires a deviation from a Monday to Friday work week.


All positions would be five day positions if the test is the number of days now worked by employes. This result was not intended by the parties. It is important to note that both the Chicago Agreement of March 19, 1949, and the Rules of the parties contain the following:



It is clear that it is not the work week of the individual employes that controls, but the "service, duties, or operations necessary to be performed the specified number of days per week."


Prior to September 1, 1949, the employes here involved were assigned to work a six-day week, Monday through Saturday (except weeks in which holidays occur), and in addition held themselves available for call over Sundays and holidays in accordance with the Call Rule (Rule 36). Employes standing by on Sundays and holidays were paid a minimum of four hours at the pro rata rate for the Sunday or holiday on which held subject to call, and if called, they were additionally paid in accordance with Rule 35. The Call Rules were continued without change after September 1, 1949, when the 40hour week commenced. It thus appears that prior to the establishment of the 40-hour week, the parties apparently recognized that the duties and operations to be performed by signal maintainers and assistant signal maintainers were such that employes were needed six days each week and on alternate weeks signal maintainers were needed seven days a week.


It is. of course, an obvious fact that interlocking plants and CTC (Centralized Traffic Control) systems are in service both night and day, seven days a week, at strategic points on the Carrier's lines and that trains are operated both night and day seven days a week. These facts did not change when the 40-hour work week was adopted.

5545-20 533

In Award 5393 involving the same Organization but a different Carrier and the same issue as here presented, we said:



The facts in this case support the Carrier's position as strongly as the facts involved in Award 5393.


The employes have not shown that the nature of the operations is such that the employes will not be needed six days a week at these points. On the contrary, the record made before this Board would bring this case within the language of Rule 30 (c) (2), " **** the nature of the work is such that employes will be needed six days each week **** ."



·day positions. In this connection we call attention to the statements contained in the letter of February 27, 1949, written by the Emergency Board in response to the Carrier's Conference Committee and the Sixteen Cooperating Railway Labor Organizations. We call attention particularly to the following paragraph:



On behalf of the Employes it is contended that even if the positions are six day positions, Rule 30 (c) (4) makes elaborate provisions for relief positions both regular and irregular, and that the parties neither expressly nor by implication stated the rules pertaining to relief assignments were an alternative solution. In effect, what is argued for is that the Carrier should have used relief workers instead of providing for staggered work weeks.


We have carefully considered the history and background of the 40-Hour Week Agreement and the language of the Agreement. We cannot agree that an effort to establish relief positions is a condition precedent to staggering work weeks as contemplated under Rule 30. To begin with, there is nothing in the language of Rule 30 which specifically requires that an effort be made to provide relief assignments before staggering work weeks. While it is true

5545-21 534

that both the provisions for staggering work weeks and providing relief assignments are part of the same Rule, the use of one is not made conditional on the other.

The letter of February 27, 1949, of the Emergency Board clearly indicates that the Board considered staggered work weeks and relief assignments as alternatives and as serving different although related purposes. Thus the Board stated:







It will be noted that the two items in question are referred to as elements of the 40-hour program. Staggering work weeks were intended as a device to reduce the expense to the Carrier of converting from a six-day to a five-day week. Relief assignments were intended as a device to eliminate work by regular employes on the sixth and seventh days at overtime rates. One of the objectives of the 40-hour week, that of spreading work, would be frustrated if regular employes were so used. Hence, the admonition of the Board, "The least desirable solution, to be used only as a last resort, in keeping with the main purpose of the Board, would be to work some regular employes on the 6th and 7th days at overtime rates and thus withhold work from additional relief men." Thus the Emergency Board in recommending Rule 30 (c) (4) undoubtedly had in mind the situation when the work week could not be

5545-22 5;j5

staggered and the carrier would be tempted to work the regular employes on the rest days at overtime rates, or where the amount of work necessary to be performed on the rest days was in excess of that which could be performed by the employes assigned to work on such days.


Moreover, it is difficult to reconcile the contention that staggered work weeks and relief assignments are dependent provisions with the final decision of the Emergency Board which denied the Organization's request for a uniform Monday to Friday work week with Saturdays and Sundays as the rest days for all regular employes. The decisions establishing the 40-hour work week and subsequent opinions clearly show that the provision for staggered work weeks was intended among other reasons to reduce expense to the carriers. The Board which wrote the 40-hour decision expressly rejected the Organization's request for a uniform Monday to Friday work week. Various estimates of costs of the 40-hour work week to the carriers were considered. The Board in estimating the cost did so on the basis of staggered work weeks, after both parties had submitted estimates of both staggered and non-staggered 40-hour weeks. (Report to the President by the Emergency Board - NMB Case A-2953, pp 18-20, 23, 30, 31.) If the Carrier has any burden under Rule 30 (c)(4), it is to show that regular employes must be worked overtime on Saturday and Sunday in lieu of establishing a regular relief assignment.


While we find we must deny the instant claim, we do not wish to leave the impression that the Carrier is free to establish 6 or 7 day positions at will. The Organization may freeely challenge assignments with staggered work weeks if the Carrier's operational requirements do not require staggered work weeks.


Consistent with the policy of this Board that an award should be limited to the precise issue presented to the Board in the particular case, our decision deals exclusively with the claim made relative to the particular positions here involved and is not intended as a general precedent.


FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:


That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;


That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and









ATTEST: A. I. Tummon
Acting Secretary

Dated at Chicago, Illinois, this 8th day of November, 1951.