Award Number 5545
Docket Number SG-5303
NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
Alex Eleon, Referee
PARTIES TO DISPUTE:
BROTHERHOOD OF RAILROAD SIGNALMEN OF AMERICA
SOUTHERN RAILWAY COMPANY
STATEMENT OF CLAIM:
Claim of the General Committee of the Brotherhood of Railroad Signalmen of America on the Southern Railway Company:
(a) That the Carrier violated and continues to violate the Signalmen's Agreement when it assigned rest days of Sunday and Monday,
since September I, 1949, to certain employes working periods of five
days each week, except when holidays occur.
(b) That these certain employes should have been assigned Saturdays and Sundays as their rest days.
(c) That each employe affected and improperly laid-off on Mondays be paid eight (8) hours at his straight-time rate for all such
Mondays not worked.
(d) That each employe affected and improperly assigned to work
on Saturdays be paid the difference between eight (8) hours straighttime he was paid for and eight (8) hours at the time and one-half
rate claimed.
EMPLOYES' STATEMENT OF FACTS:
Following the negotiation of
rules, dated March 19, 1949, by a National Conference Committee establishing
a shorter work week consisting of five eight-hour days, the Carrier placed
into effect, as of September 1, 1949, the shorter work week.
Hourly paid employes on five-day positions were assigned Saturday and
Sundays as their rest days, except that occupants of certain positions were
improperly assigned Sundays and Mondays as their rest days.
The positions assigned rest days of Sundays and Mondays on the territory
under the supervision of Mr. M. A. Otterbourg are shown in the bulletin
reproduced herewith:
"SOUTHERN RAILWAY SYSTEM
OFFICE OF SIGNAL & ELECTRICAL SUPERINTENDENT
CHARLOTTE, N. C.
August 22, 1949.
"TO ALL EMPLOYES SIGNAL & ELECTRICAL DEPARTMENT:
"Effective September 1, 1949, the 40-hour week will be inaugurated and the following employes are assigned Saturdays and Sundays each week:
5545-1s
531
Division, National Railroad Adjustment Board has no authority to sustain the
claim
For all of the reasons given, the claim should in all things be denied and
the Carrier respectfully requsts that the Board so hold.
(Exhibits not reproduced.)
OPINION OF BOARD:
We are called upon in this dispute to interpret
the Forty-Hour Week rules for non-operating employes.
The Claimants challenge the Carrier's action in staggering the positions
of signal maintainers and assistant signal maintainers at nine stations, and
establishing for the employes there employed a work week from Tuesday
through Saturday, with Sunday and Monday as rest days.
In essence, the position of the Employes is that the claimants are filling
positions, the duties of which can reasonably be met in five days; that such
positions are five-day positions coming within Rule 30(c)(I), and that the
assigned work week should therefore have been Monday through Friday with
Saturday and Sunday as rest days.
The Carrier's position briefly is that the positions in question are six day
positions and that the work weeks in question were staggered in order to meet
the Carrier's operational requirement.
The relevant portions of the rules in question read as follows:
"RULE 30.
(b) The expressions 'positions' and 'work' when used in this
agreement refer to service, duties, or operations necessary to be performed the specified number of days per week, and not to the work
week of individual employes.
(c) The carriers will establish effective September 1, 1949, for
all employes, subject to the exceptions contained in Article II of the
Chicago Agreement of March 19, 1949, a work week of 40 hours,
consisting of five days of eight hours each, with two consecutive days
off in each seven; the work weeks may be staggered in accordance
with the carrier's operational requirements; so far as practicable the
days off shall be Saturday and Sunday. The foregoing work week
rule is subject to the provisions of the Chicago Agreement of March
19, 1949.
(1)
Five-Day Positions:
On positions the duties of which can reasonably be met in five
days, the days off will be Saturday and Sunday.
(2)
Six-Day Positions:
Where the nature of the work is such that employes will be
needed six days each week, the rest days will be either Saturday
and Sunday or Sunday and Monday.
(3)
Seven-Day Positions:
On positions which have been filled seven days per week any
two consecutive days may be the rest days with the presumption in
favor of Saturday and Sunday. Where the nature of the work is such
that it is necessary and essential to the service for a position to be
filled seven days each week, such position may be established.
5545-19
(4)
Regular Relief Assignments:
All possible regular relief assignments with five days of work
and two consecutive rest days will be established to do the work
necessary on rest days of assignments in six or seven-day service or
combinations thereof, or to perform relief work on certain days and
such types of other work on other days as may be assigned under
this agreement.
Assignments for regular relief positions may on different days
include different starting times, duties and work locations for employes of the same class in the same seniority district, provided they
take the starting time, duties and work locations of he employe or
employes whom they are relieving.
(5)
Deviation from Monday-Friday Week:
If in positions or work extending over a period of five days per
week, an operational problem arises which the carrier contends cannot be met under the provisions of paragraph (c) (1) of this Rule 30,
and requires that some of such employes work Tuesday to Saturday
instead of Monday to Friday, and the employes contend the contrary, and if the parties fail to agree thereon, then if the carrier
nevertheless puts such assignments into effect, the dispute may be
processed as a grievance or claim under agreement rules."
The Employes argue that since signalmen now work five days a week,
the positions are five-day positions under the agreement, and that in any
event there is nothing about the work of signalmen that requires a deviation
from a Monday to Friday work week.
All positions would be five day positions if the test is the number of days
now worked by employes. This result was not intended by the parties. It is
important to note that both the Chicago Agreement of March 19, 1949, and
the Rules of the parties contain the following:
"The expressions 'positions' and 'work' when used in this agreement refer to service, duties, or operations necessary to be performed
the specified number of days per week, and not to the work week of
individual employes." (Rule 30(b)-Parties' agreement and Article
II, Section 1-Note.)
It is clear that it is not the work week of the individual employes that
controls, but the "service, duties, or operations necessary to be performed the
specified number of days per week."
Prior to September 1, 1949, the employes here involved were assigned to
work a six-day week, Monday through Saturday (except weeks in which
holidays occur), and in addition held themselves available for call over Sundays and holidays in accordance with the Call Rule (Rule 36). Employes
standing by on Sundays and holidays were paid a minimum of four hours at
the pro rata rate for the Sunday or holiday on which held subject to call, and
if called, they were additionally paid in accordance with Rule 35. The Call
Rules were continued without change after September 1, 1949, when the 40hour week commenced. It thus appears that prior to the establishment of the
40-hour week, the parties apparently recognized that the duties and operations to be performed by signal maintainers and assistant signal maintainers
were such that employes were needed six days each week and on alternate
weeks signal maintainers were needed seven days a week.
It is. of course, an obvious fact that interlocking plants and CTC (Centralized Traffic Control) systems are in service both night and day, seven
days a week, at strategic points on the Carrier's lines and that trains are
operated both night and day seven days a week. These facts did not change
when the 40-hour work week was adopted.
5545-20
533
In Award 5393 involving the same Organization but a different Carrier
and the same issue as here presented, we said:
"Carrier makes an impressive case for the need for six-day signal
maintenance service on its lines. Further, and of great significance, is
the fact that it is not something born as of September 1, 1949, or of
the date of the ruling by the Presidential Emergency Board imposing
the five-day work week. Instead it is based upon operational practices
which have
existed over a period of many years. We cannot
presume that Carrier long indulged in a useless waste of funds and no
sudden technological change is shown to have occurred in 1949 to
alter the need. There is nothing shown by the record which convinces us that Carrier acted arbitrarily in continuing the six-day
signal service practice. Accordingly, we find that the nature of the
work is such that employes will be needed six days each week and
the case is governed by Rule 11 (b) (2) and not Rule 11 (b) (1).
Carrier's determination of the question is reasonable and must stand."
The facts in this case support the Carrier's position as strongly as the
facts involved in Award 5393.
The employes have not shown that the nature of the operations is such
that the employes will not be needed six days a week at these points. On the
contrary, the record made before this Board would bring this case within the
language of Rule 30 (c) (2), " **** the nature of the work is such that employes will be needed six days each week **** ."
We hold that the positions in question are six day positions and not five
·day positions. In this connection we call attention to the statements contained
in the letter of February 27, 1949, written by the Emergency Board in
response to the Carrier's Conference Committee and the Sixteen Cooperating
Railway Labor Organizations. We call attention particularly to the following
paragraph:
"The next question relates to the staggering of the work weeks
and Saturdays and Sundays as the days of rest. Obviously, if the
work week is staggered some employes cannot have these specific
days off. That the Board expected deviations from this pattern is
made abundantly clear by its repeated use of the expressions 'staggered work week,' 'in accordance with operational requirements,' and
'so far as practical.' The great variety of conditions met in the railroad system of the country and even varied conditions on a single
railroad require flexibility on this matter. The tenor and substance
of the Board's discussions and recommendations show definitely that
the Board intended to permit the Carriers to stagger work weeks.
In contrast with the obligation of the Carriers to sustain the burden
of proof in the matter of non-consecutive rest days, it is for the Employes here to show that some particular operational requirements
of the carriers are not better met by having the work weeks staggered." (Underlining ours)
On behalf of the Employes it is contended that even if the positions are
six day positions, Rule 30 (c) (4) makes elaborate provisions for relief positions both regular and irregular, and that the parties neither expressly nor by
implication stated the rules pertaining to relief assignments were an alternative solution. In effect, what is argued for is that the Carrier should have
used relief workers instead of providing for staggered work weeks.
We have carefully considered the history and background of the 40-Hour
Week Agreement and the language of the Agreement. We cannot agree that
an effort to establish relief positions is a condition precedent to staggering
work weeks as contemplated under Rule 30. To begin with, there is nothing
in the language of Rule 30
which specifically
requires that an effort be made
to provide relief assignments before staggering work weeks. While it is true
5545-21
534
that both the provisions for staggering work weeks and providing relief assignments are part of the same Rule, the use of one is not made conditional
on the other.
The letter of February 27, 1949, of the Emergency Board clearly indicates
that the Board considered staggered work weeks and relief assignments as
alternatives and as serving different although related purposes. Thus the
Board stated:
"Recommendation No. 1 deals with the establishment of a shorter
work week which was the primary aim of the Board. It is well to
bear this in mind. The Board intended to have the employes achieve
a work week of five 8-hour days, without loss in earnings. Its purposes were two: (1) to give employes 2 days rest each week and
(2) to spread and maintain employment. Its purpose was not to
obtain more pay for employes through overtime on the 6th and 7th
day of the week, and it sought through the penalty provisions to discourage such work schedules.
"A work week of 40 hours, consisting of 5 days of 8 hours each,
with 2 consecutive days off in 7 was recommended. This represents
the major difference between the parties, because on page 18 of the
report, following a description of the continuous nature of railroad
operations and of the methods used in other industries, the Board
said:
`Consistent with their operational requirements, the Carriers should allow the employes two consecutive days off in
seven and so far as practicable these days should be Saturdays and Sundays.'
"This sentence if read and compared with other expressions in
the report has a plain meaning. `Consistent with their operational requirements' qualifies the entire 40 hour program recommended. That
program has a combination of elements: five 8-hour days, 40 hours
per week, two consecutive days off each week, Saturdays and Sundays as the rest days, staggered work-weeks and relief assignments.
"When an operational problem is met it does not automatically
follow that the solution is to make the days off non-consecutive.
other possible solutions may be found by hiring additional relief or
extra men who may be used to relieve on combinations of 6 day and
7 day positions. Days other than Saturday and Sunday may be assigned as rest days, or weekly rest days may be accumulated and
longer consecutive rest time substituted periodically. Some of the
relief or extra men may have non-consecutive rest days, and some
employes may be kept on duty for overtime work. Other suitable or
practical plans may suggest themselves to one of the parties and meet
with the approval of the other. The least desirable solution, to be
used only as a last resort, in keeping with the main purpose of the
Board, would be to work some regular employes on the 6th and 7th
days at overtime rates and thus withhold work from additional relief
men."
It will be noted that the two items in question are referred to as elements
of the 40-hour program. Staggering work weeks were intended as a device to
reduce the expense to the Carrier of converting from a six-day to a five-day
week. Relief assignments were intended as a device to eliminate work by
regular employes on the sixth and seventh days at overtime rates. One of
the objectives of the 40-hour week, that of spreading work, would be frustrated if regular employes were so used. Hence, the admonition of the Board,
"The least desirable solution, to be used only as a last resort, in keeping with
the main purpose of the Board, would be to work some regular employes on
the 6th and 7th days
at overtime rates and thus withhold work from additional relief men." Thus the Emergency Board in recommending Rule 30 (c)
(4) undoubtedly had in mind the situation when the work week could not be
5545-22
5;j5
staggered and the carrier would be tempted to work the regular employes on
the rest days at overtime rates, or where the amount of work necessary to be
performed on the rest days was in excess of that which could be performed
by the employes assigned to work on such days.
Moreover, it is difficult to reconcile the contention that staggered work
weeks and relief assignments are dependent provisions with the final decision
of the Emergency Board
which denied
the Organization's request for a uniform Monday to Friday work week with Saturdays and Sundays as the rest
days for all regular employes. The decisions establishing the 40-hour work
week and subsequent opinions clearly show that the provision for staggered
work weeks was intended among other reasons to reduce expense to the
carriers. The Board which wrote the 40-hour decision expressly rejected the
Organization's request for a uniform Monday to Friday work week. Various
estimates of costs of the 40-hour work week to the carriers were considered.
The Board in estimating the cost did so on the basis of staggered work weeks,
after both parties had submitted estimates of both staggered and non-staggered 40-hour weeks. (Report to the President by the Emergency Board -
NMB Case A-2953, pp 18-20, 23, 30, 31.) If the Carrier has any burden under
Rule 30 (c)(4), it is to show that regular employes must be worked overtime
on Saturday and Sunday in lieu of establishing a regular relief assignment.
While we find we must deny the instant claim, we do not wish to leave
the impression that the Carrier is free to establish 6 or 7 day positions at will.
The Organization may freeely challenge assignments with staggered work
weeks if the Carrier's operational requirements do not require staggered work
weeks.
Consistent with the policy of this Board that an award should be limited
to the precise issue presented to the Board in the particular case, our decision
deals exclusively with the claim made relative to the particular positions here
involved and is not intended as a general precedent.
FINDINGS:
The Third Division of the Adjustment Board, after giving
the parties to this dispute due notice of hearing thereon, and upon the whole
record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Carrier did not violate the agreement.
AWARD
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST: A. I. Tummon
Acting Secretary
Dated at Chicago, Illinois, this 8th day of November, 1951.