NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood, that:
EMPLOYES' STATEMENT OF FACTS: Track Foreman T. Hoey and Trackmen P. Carroll, A. Ferraro, T. Powers and M. Doyle were assigned to and held seniority on Section #7 of the Boston and Maine Railroad.
Track Foreman T. Hoey and his crew have a regular five day a week assignment, Monday through Friday .
On Saturday, April 23, 1949, the Carrier assigned an Extra Crew to pick up coal on Section #7.
Track Foreman Hoey and his crew were available but were not called to perform this service.
A claim was filed in behalf of Track Foreman Hoey and his crew for compensation at their respective time and one-half rate of pay for three (3) hours on April 23, 1949 because of the Carrier's improper assignment.
The agreement in effect between the two parties to this dispute dated May 15, 1942 and subsequent amendments and interpretations are by reference made a part of this Statement of Facts. Reprinted January 2, 1951).
POSITION OF EMPLOYES: Rules 1, 2 and 3 (a) of the effective agreement read as follows:
to remove this coal with a crane at the earliest possible moment as its presence prevented use of the lead track.
There is before the Third Division, at this time, a dispute, submitted ex parte by the Employes, party to this dispute, identified by Acting Secretary, Mr. A. 1. Tummon, as follows:
The Position of Carrier, as set forth in Carrier's answer to the aforesaid ex parts submission of the Employes in the quoted dispute, is equally applicable to this dispute. Rather than burden this docket with a repetition of Carrier's entire argument, Carrier's Position in the above quoted dispute is hereby made a part of Carrier's Position in this docket.
In addition to the foregoing there is the added feature here that the work performed by the regular extra crew, in this docket, was definitely in the category of emergency work. Carrier's lead track into Mystic Wharf Yard was blocked and could not be used until a crane and crew removed the accumulated coal therefrom.
All data and arguments herein contained have been presented to the Committee in conference and/or correspondence.
OPINION OF BOARD: This case is concerned with a claim of the System Committee of the Brotherhood on behalf of Track Foreman T. Hoey and his crew for three hours' pay at penalty rates for Saturday, April 23, 1949. It is asserted by petitioner that respondent Carrier violated the effective Agreement when it failed to call claimants for work on the date in question.
There is no controversy between the parties with respect to the essential facts involved in the instant situation. Both parties state that the principle involved in this case is the same as the one involved in Dockets MW-5688 and MW-5689, on which Awards are made this day.
The issue is primarily one of interprting the relevant rules of the Schedule with respect to the rights of Claimant Crew to the work involved on April 23, 1949. Petitioner contends that Claimant Crew, by reason of seniority, owned the right to perform the work here at issue. The Carrier denies that Claimant Crew had any such exclusive right to the work. It is contended that the Carrier acted properly and within the provisions of the Agreement when it had the work in question performed by a regular extra crew rather than the section crew. The Carrier states that over a period of many years, the regular extra crews have had rights to certain work, and that the section crews cannot, therefore, be said to have the exclusive right to work upon their respective sections.
The Third Division has had before it in earlier dockets involving these same parties and the same contract, the identical issue posed in this docket. 5950-a 616
and in dockets MW-5688 and MW-5689. These earlier dockets were disposed of with Award 4700 and 5261.
In this case on which Award 4700 was made these same parties took positions to some extent opposite from their respective positions in the instant case. In Award 4700 the Carrier's position was upheld and it was determined that the regular section crew which Carrier had used was entitled to the work.
In Docket MW-5229 resulting in Award 5261, the issue in dispute was virtually identical with the issue in the instant case. In that case, as in the instant case, Petitioner contended that the regular section crew had the primary right on the bases of Rule 5-A to the work on the section. The Division sustained the claim, and stated as follows:
The respondent Carrier in the instant case requests that the Division reverse its holding in Award 5261. Therefore, we must ask whether the decision in Award 5261 was so manifestly wrong that it should not be reversed. Further, are there sufficient variations in the facts in the instant case to justify a different conclusion than that given in Award 5261?
With respect to the second question, we find that the facts are not suffciently different to justify a different conclusion. The Carrier's contention that an emergency existed is not convincing. With respect to the first question, no evidence or argument has been submitted in the instant case tr. justify a conclusion that Award 5261 was manifestly wrong. It appears that the Division had before it in Award 5261 virtually all of the considerations which have been submitted in the instant case.
In view of these considerations an affirmative Award is justified. Under the circumstances obtaining, and it keeping with previous Awards of the Division, payment should be at pro rata rates. 5950-7 617