PARTIES TO DISPUTE:

BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYES
NORTHERN PACIFIC RAILWAY COMPANY

STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:




EMPLOYES STATEMENT OF FACTS: In connection with a proposed change in the curvature of a portion of the Carrier's tracks west of the Spokane Passenger Station, it was found that Bridge 1.4 over Seventh Avenue would have to be relocated, necessitating the West End of the Bridge to be moved in a northerly direction for approximately twenty-five (25 feet at the West End and for approximately forty-five (45) feet at the East End.


Because the existing Bridge 1.4 was a pile and timber construction and because its relocation would seriously interfere with the Carrier's train movements, the Carrier concluded that it would be economically sound and advantageous to construct a new steel-bridge with a concrete slab deck at the point where bridge was to be relocated, since such construction would provide a heavier and stronger bridge and one which would better serve the heavier traffic and the anticipated future requirements at this point. In addition, construction of the new bridge would require only the north half of the two track pile and timber bridge to be removed and taken out of service, thus permitting one track thereon to remain in service without the necessity of totally disrupting train service during relocation work on the bridge such as would be involved if the existing bridge was moved in its entirety to the new location.


Without benefit of Agreement between Management and the General Chairman, the work of constructing the new bridge was let to a contractor and performed by contractor's forces, none of which held any seniority rights under the effective Agreement. This ridge which was constructed by contract



6930-24 314










All data in support of the Carrier's position in connection with this claim has been presented to the duly authorized representative of the Employes and is made a part of the particular question in dispute.




OPINION OF BOARD: This claim comes to this Board by reason of Carrier's action in assigning the construction of Bridge 1.4 to an outside contractor. Bridge and building employes, holding seniority on the Idaho Division claim this work.


The question presented for our consideration is, was this a line change? In order to make this change, an easement was obtained from the owner of a parcel of land contiguous to the new line of railroad. A new roadbed was graded, and new ties and rail were laid for 1999 feet. The grading, placing of new ties, laying of new rail and dismantling of the old bridge was done by Maintenance of Way employes. The new bridge was built by a firm of private contractors.


A letter agreement was entered into on July 25, 1922, which reads in part:



The basic Agreement was subsequently revised on April 1, 1936 and August 1, 1943. It was later contended that Carrier had violated the Agreement by contracting certain bridge repair work to outsiders and the aforementioned revisions superseded the Letter Agreement of July 25, 1922 referred to above. Awards 3254 and 3255 answered that contention in denial awards, stating in part:


6930-25 3155

Therefore, in the new Agreement of April 1, 1952, we are constrained to say the Letter Agreement of July 25, 1922 is still in full force and effect. In the negotiations prior to the current Agreement proposed rules were suggested but were not accepted. In lieu of the Letter Agreement of July 25, 1922, the parties, however, negotiated Letter Agreement of January 31, 1952, providing in part:





Apparently this Letter Agreement relates to work customarily performed by the Maintenance of Way Department and we do not believe it extended the Scope of the Agreement.


Also see letter of February 11, 1952 to the effect that the practice concerning performance of work was not changed by the Agreement effective April 1, 1952, which apparently places the burden of proof on Employes to show that these letter agreements were violated in the instant case.


We think that the work here involved was performed on a line change and therefore does not come within the Scope of the Agreement, and are not in agreement with Petitioners' contention that the work was a relatively small change made in the curvature of existing track. Here Carrier acquired a new right of way, made a new fill, laid new ties and rails and built a new bridge containing nearly 500 tons of steel, built 1999 feet of new railroad which was separate and apart from the existing line, which must be construed to place this work in a different category than the ordinary alignment such as done by Maintenance of Way Employes.


Therefore, we conclude, that on the record here, there was no violation of rules.


FINDINGS: The Third Division of the Adjustment Board, after giving the parties to this dispute due notice of hearing thereon, and upon the whole record and all the evidence, finds and holds:


That the Carrier and the Employes involved in this dispute are respectively carrier and employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

6930-26 316

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and





    Claims denied in accordance with Opinion and Findings.


              NATIONAL RAILROAD ADJUSTMENT BOARD

              By Order of Third Division


ATTEST: (Sgd.) A. Ivan Tummon
Secretary

Dated at Chicago, Illinois, this 29th day of March, 1955.